Costs of Cairngorm railway spiral ahead of 2023 opening

- By Martin Williams

THE cost to the taxpayer of the UK’S highest railway, which shut four years ago, has soared by over three-and-a-half times to nearly £52 million – with the costs of crucial repairs spiralling. Taxpayers are having to foot the bill for the extra costs in fixing structural issues with the Scottish Government agency-owned Cairngorms mountain railway to the tune of £9m.

The 1.3 mile funicular will not now reopen for the start of this winter season and is due to relaunch early next year

Calls have previously been made for a public inquiry into the management of the Cairngorm funicular, which it was hoped would re-open in late 2022.

It has meant the ski centre above Aviemore in the Scottish Highlands will remain without its main lift for a fourth successive ski season.

THE cost to the taxpayer of the UK’S highest railway, which shut four years ago, has soared by over three-and-a-half times to nearly £52 million – with the costs of crucial repairs spiralling, it can be revealed.

Taxpayers are having to foot the bill for the extra costs in fixing the structural issues with the Scottish Government agency-owned

Cairngorms mountain railway to the tune of £9m.

The 1.3 mile funicular will not now reopen for the start of this winter season and is due to relaunch early next year – having seen costs spiral from an original price of £14.8m.

Calls have previously been made for a public inquiry into the management of the Cairngorm funicular, which it was hoped would re-open in late 2022.

It has meant the ski centre above Aviemore in the Scottish Highlands will remain without its main lift for a fourth successive ski season.

The Cairngorms are a major Scottish tourism attraction and centre for recreation with downhill hillwalkin­g and rock climbing a major draw for the 1.92m who visit the national park every year from around the world.

But the crucial funicular, which was opened in 2001 and connects a base station with a restaurant and a ski area 1,097m (3,599ft) up Cairn Gorm mountain near Aviemore, has been closed since September 2018 due to structural issues.

It has now been confirmed that the cost of repairs have risen by 56% from £16.16m to £25m.

The faults were discovered after the costs of building the funicular spiralled from £14.8m to £26.75m.

According to the Cairngorm National Park Authority strengthen­ing works to the railway viaduct involves reinforcin­g props and concrete bases beside 63 out of 94 piers.

Past concerns have been raised from within the funicular’s owner, the Scottish Government’s Highlands and Islands Enterprise agency about how it will be paid for.

HIE said it has “reallocate­d uncommitte­d funds” from a wider Cairngorm masterplan capital investment package to meet the additional costs. The Scottish Government also allocated £7m additional funding in June 2022.

HIE says it will continue to pursue legal action against the funicular’s original designer and constructi­on contractor in the Court of Session, in a bid to recoup public funding.

The Herald revealed the early stages of the £14.5m claim last year against the now owners of Morrison Constructi­on, Galliford Try Infrastruc­ture Limited and Inverness-based AF Cruden Associates Limited, the civil and structural engineers for the scheme which had been taken over by Glasgowbas­ed Arch Henderson.

The decisions over the contracts for the funicular were hit with allegation­s of cronyism and financial mismanagem­ent that led to an investigat­ion after chief executive of HIE, Iain Robertson, announced in 2000 that he would be leaving to become director for corporate developmen­t for Morrison plc, an Edinburgh-based constructi­on company founded and once chaired by one of Scotland’s wealthiest men Sir Fraser Morrison.

In five years HIE had awarded a number of Morrison contracts including that for the building of the controvers­ial railway up Cairngorm which they eventually received more than £10m for.

Morrisons were awarded the funicular contract in 1999, a year after Sir Fraser left HIE.

Audit Scotland said there was no conflict of interest.

Scottish Conservati­ves’ Highlands and Islands MP Edward Mountain MSP said: “One questions who has been managing this asset for the country. Would we have been better installing a different form of lift to get the capacity we need at a lower cost? Also, how much will the previous operator contribute to the final repair bill? If the funicular is ready during winter 2023 then this would be a huge boost for a local tourism industry.

“While I am pleased, following my calls earlier this year, that the Scottish Government committed a further £7m to the repairs, I am however concerned that HIE have had to reallocate funding from the Cairngorm masterplan investment package. Many will be left wondering what knock-on impact that will now have on the masterplan and I will be seeking further clarity on this matter.”

Many will be left wondering what knock-on impact that will now have on the masterplan

 ?? ?? Repairs on the railway
Repairs on the railway
 ?? Pictures: Peter Jolly ?? The Funicular railway at Cairngorm Mountain, which has been undergoing repairs for a couple of years
Pictures: Peter Jolly The Funicular railway at Cairngorm Mountain, which has been undergoing repairs for a couple of years
 ?? ?? Cairngorm Mountain where repair work is being done
Cairngorm Mountain where repair work is being done
 ?? ?? A helicopter lifting supplies up Cairngorm Mountain
A helicopter lifting supplies up Cairngorm Mountain