The Herald on Sunday

Abandon ships? Concerns as leaked report shows massive Ferries will never be used increase in serious faults

Alarming new documents seen by The Herald on Sunday reveal ‘highest level risk’ alerts in vital areas such as escape routes and fuel systems – and admit CMAL may not accept the vessels

- By Martin Williams

THE two vessels at the centre of Scotland’s ferry scandal may never see service as internal risk reports have uncovered serious concerns that casts doubt they will ever be accepted for use.

New documents seen by The Herald on Sunday reveal highest-level risk concerns in five key areas, with new project “non-conforming issues” surroundin­g escape routes, stability, and the fuel system.

The April analysis from Ferguson Marine reveals the number of faults that remain outstandin­g on the ferries has risen from 166 before nationalis­ation to 237 in March. Some 65 per cent of them relate to safety, maintainab­ility, or specificat­ion requiremen­ts.

New internal documents from nationalis­ed shipyard firm Ferguson Marine admit a serious risk that CMAL may not accept the vessels for ferry operator CalMac’s lifeline services to island communitie­s.

CMAL, in the document seen by The Herald on Sunday, criticises management systems in place and said the most pressing risk issue was the “failure to completely understand the actual remaining works that must be completed in order to deliver each vessel”.

Of the faults issues, CMAL states: “The resolution of these is considered crucial prior to vessel handover. The impact of which remains unknown and not factored into the vessel programme.

It said the yard process “continues to apportion no special priority” to the outstandin­g faults – termed as owner observatio­n reports (OORs).

“The emphasis given over to statutory priority one issues should warrant far greater attention,” the analysis states.

‘Derisk design’

FERGUSON Marine has stated that it is to continue to work with bodies such as the Maritime and Coastguard Agency and maritime classifica­tion society Lloyd’s Register which oversee vessel seaworthin­ess to “derisk the design and agree acceptable concession­s”. One MP has now raised concerns over a “fundamenta­l error” which has meant pumps are unable to deliver fuel to the the main engines.

It comes after it emerged ministers sanctioned a milestone payment of £1.2 million for the successful launch of one of the ships, the Glen Sannox, by Nicola Sturgeon in 2017.

CMAL became legally obliged to pay out 85% of the £97m initial price of both the vessels – Glen Sannox and the unnamed Hull 802 – to the pre-nationalis­ed, Jim McColl-led Ferguson Marine in advance despite having serious concerns about its delivery. This week, it also emerged that the ferry fiasco contract was finally approved by then-transport minister Derek Mackay.

Officially, Glen Sannox and Hull 802 will be delayed until at least next year – over five years later than planned – while costs have at least doubled from £97m to £250m. But the April risk assessment reveals there was “no agreed solution” over OORs regarding one of the vessels, Glen Sannox, which have to be rectified as part of the contract.

It revealed a serious risk that if all OORs are “not agreed as closed” with CMAL then acceptance of the vessel “will be difficult to achieve”. It was given a 250 risk score, understood to be the highest level.

Up to August 16, 2019, the date at which Ferguson Marine under tycoon Mr McColl entered administra­tion, CMAL had issued 346 OORs, faults which have to be rectified as part of the contract. Of these, Ferguson Marine had resolved 180 and 166 were outstandin­g.

Increased faults

AT the end of January 2022, there were 175 outstandin­g OORs including incomplete structural work which will increase costs and delays – nine more than when the Scottish Government took control of the yard at the end of 2019. According to the latest CMAL analysis, this has risen to 237.

The CMAL progress report said: “Yardwide inefficien­cies in onboard production supervisio­n, project management’s lack of understand­ing of the remaining project deliverabl­es, and repetitive rework caused by inadequate constructi­on design output all remain substantia­l risks that will cause further delays if allowed to continue unchecked. To remain objective, it must be stressed that the current management systems’ routine failure to recognise and control risk-based delays must be the subject of immediate detailed analysis.”

It said further risk issues that need to be “seriously considered” included monitoring and reporting “key production metrics in support of sound project decisions making”.

CMAL also raised concern about the risk impact associated with “sustained high levels of rework driven by continued adherence to a policy that does not advocate in-house review of third-party design input”.

Major faults uncovered in the Ferguson Marine checks included an issue with a valve block with “potential large cost” to rectify. Also listed is an issue with a diesel fuel system overflow venting arrangemen­t. There was also a “risk of late change due to design errors. These errors may be [a] mistake, missed scope or non-conformanc­es to requiremen­ts/ spec,” internal papers reveal.

It has resulted in a plan for a complete review of plans with CMAL.

In the near seven years since the ferries contract was awarded, the yard has been saved from administra­tion by the Scottish Government, and the estimated delivery of two vessels has been pushed back by over five years, along with an increase in costs from £97m to at least £250m. The Glen Sannox and Hull 802 are now not expected to be completed until between March and May 2023 and between October and December 2023 respective­ly at the earliest.

Risk CMAL ‘won’t accept vessels’

THE nationalis­ed Ferguson Marine has told Audit Scotland that if multiple issues with the vessels are not resolved, “there is a risk CMAL will not accept the completed vessels”. The two new dualfuel ferries, which were meant to be identical, were once hailed as a step

It must be stressed that the management systems’ routine failure to recognise and control risk-based delays must be the subject of immediate detailed analysis

towards a greener future for Scotland’s state-owned CalMac ferry fleet as they were to be the first UK-built ships capable of running off liquefied natural gas, or LNG, as well as convention­al diesel.

The April assessment shows a new high-risk issue involving modificati­ons to the storage of liquefied natural gas fuel for use on the ships as facilities had not been created and risk assessment­s had not yet been undertaken.

No ground has reportedly been broken on the £5m contract for the bunkering facilities at Ardrossan and Uig which were due to be ready this year.

There were also risks associated with a “non-compliant” axilock – which is used to connect plain-end pipe lengths together with speed and ease without the need for gluing or fusion technology.

Ferguson Marine has had to review the status of all axilocks on the ship and change them if needed along with a further examinatio­n of the fuel system.

Supply issues

ANOTHER high-risk factor was a “lack of buy-in from the workforce to deliver the plan and employee engagement sessions were put in place. It goes: “This includes the fitness of our workforce to deliver the challenge ahead [mature workforce].” It even reveals a supply chain issue because of the sanctions against Russia and Belarus in the wake of the war in Ukraine.

Former justice secretary Kenny MacAskill MP, now Alba Party deputy leader, said of the continued issues around delivery of the vessels: “You couldn’t make it up.” He was particular­ly concerned about an emerging issue with the fuel tank pipework and the supply of marine gas oil to the main engines.

According to CMAL analysis, work has started on proposed modificati­ons to “correct” the fuel system installati­on on

Glen Sannox with the focus on fitting a missing pipe and pipe supports.

“Progress is slow in all areas. The fuel oil piping and storage tank installati­on in the emergency generator space are still not complete,” it said.

Mr MacAskill said: “This is yet another setback for the communitie­s. But again it’s nothing to do with the quality of work at Ferguson’s and everything to do with procuremen­t. Blame rests with CMAL who are not fit for purpose and should be scuttled. There are ships available that can be built and which are the right sort. They can be built in Scotland and for less than the current vessels. They’re wanted by communitie­s and it’s time for radical change. CMAL and Ferguson’s current management must go.”

‘Committed’

A CMAL spokesman said: “We are confident that outstandin­g issues can and will be rectified, and the vessels completed to enter service. The appointmen­t of a permanent chief executive at the shipyard has been a welcome developmen­t, and we have further strengthen­ed collaborat­ion between our senior teams via the secondment of our senior vessels project director, which will provide added experience and improve decision-making. We will continue to work in partnershi­p and remain committed to the completion of the two ferries.”

A spokespers­on for Ferguson Marine (Port Glasgow) said: “We are aware of legacy issues and as such have factored them into the amended plan being driven by the new CEO with the support of management and working closely with workforce representa­tives and CMAL to ensure high standards of workmanshi­p, health and safety compliance, and morale.”

A Scottish Government spokespers­on said: “The Economy Secretary [Kate Forbes] has been crystal clear on what she expects from Ferguson Marine in terms of delivering the ferries, as well as turning the business around to be competitiv­e. Until those vessels are serving the communitie­s for which they were built, we will not let up in our drive and determinat­ion to get them finished and delivered. The board recognises that and has been driving that improvemen­t process within the business. A senior member of CMAL staff has recently been seconded to Ferguson Marine management to support delivery of the vessels and resolve any outstandin­g issues. Working alongside the new chief executive, this has driven significan­t improvemen­ts already. We remain fully committed to completing these vessels, and it is important that the workforce at Ferguson’s also know that we remain committed to this work.”

 ?? ??
 ?? ??
 ?? ?? Former justice secretary Kenny MacAskill referred to ‘another setback for communitie­s’ over the latest ferries fiasco
Former justice secretary Kenny MacAskill referred to ‘another setback for communitie­s’ over the latest ferries fiasco
 ?? ?? Glen Sannox and Hull 802 are years behind schedule and well over budget
Glen Sannox and Hull 802 are years behind schedule and well over budget

Newspapers in English

Newspapers from United Kingdom