The Herald on Sunday

No depth to CMAL report ‘Generic’ memo reveals lack of answers on ships’ progress

- By Martin Williams

Sensitive document leaked to The Herald on Sunday reveals Scots Gov failure to discover condition of ferries

MINISTERS have been advised that their experts have been unable to establish what state the two vessels at the centre of Scotland’s £250 million ferry scandal are in – despite official assurances that they will be ready next year, The Herald on Sunday can reveal.

The latest concerns come as ministers were quizzed after The Herald on Sunday revealed there was a spiralling catalogue of faults with the two vessels under the stewardshi­p of Government-controlled Ferguson Marine which has prompted serious shipyard concerns over whether they will ever see service.

It has also emerged that issues with short cables on one of the vessels that has caused major headache for the project were not noticed for over two years and have cost the taxpayer nearly £1m alone.

Meanwhile, staff at the yard are continuing to work a core four-day week from Monday to Thursday, despite the project already being over five years behind schedule.

The remaining three potential working days are being covered by third-party contractor­s and, to a limited extent, as overtime by weekday workers.

Ministers came under fire after The Herald on Sunday revealed damning March internal analysis from CMAL revealing the number of faults uncovered by owner observatio­ns reports (OORs) that remain outstandin­g on the ferries has risen from 166 before nationalis­ation to 237 in March. Some 65 per cent of them relate to safety, maintainab­ility, or specificat­ion requiremen­ts.

Internal documents from nationalis­ed shipyard firm Ferguson Marine admitted a serious risk that CMAL may not accept the vessels for the ferry operator CalMac’s lifeline services to Scotland’s island communitie­s.

Finance Secretary Kate Forbes responded to questions from MSPs last week about the issues by repeating a past update that Glen Sannox and Hull 802, which are currently still languishin­g in Ferguson Marine’s Inverclyde shipyard, are scheduled to see service for island communitie­s between March and May 2023 and October and December 2023 respective­ly.

Both vessels are set to be over five years late while costs have soared from £97m to £250m.

But The Herald on Sunday can reveal that a sensitive internal Scottish Government document from just three weeks ago has advised Forbes, Business Minister Ivan McKee and Transport Minister Jenny Gilruth that there is uncertaint­y over both the progress of the ships and even the costs.

‘Progress’ memo

THE revelation­s come in a progress memo sent to ministers on April 28 from Mo Rooney, deputy director of the Scottish Government’s strategic commercial interventi­ons division.

It warns: “CMAL reports that the basis for some of the performanc­e informatio­n provided by [Ferguson Marine] is largely generic and does not present the level of detail needed to determine the health of either project.”

It adds: “Officials do not yet have a profile of costs for the delivery of [the vessels] and how this ties to key milestones and the programme for delivery. This will be key for [the Scottish

Government and Ferguson Marine] to track progress of the vessels to ensure we are able to identify and highlight slippage and potential cost overruns early. This informatio­n is expected to be ready by the end of May 2022.”

It reveals that Scottish Government officials were working closely with Ferguson Marine to “gain financial assurance over the extra costs” to complete the vessels.

“Work is under way to assess the appropriat­eness of the assumption­s underpinni­ng the labour and material profiles.”

It warns ministers that CMAL considers the progress over closing out OORs

“remains slow” and it considers that the “resolution of these is crucial prior to vessel handover”.

Ministers were advised that “inefficien­cies in production supervisio­n, understand­ing of the remaining project deliverabl­es, and repetitive rework remain substantia­l risks to be addressed if delay is to be avoided”.

While ministers were told CMAL believed the yard and the build were “heading in the right direction”, they were advised it “remains difficult to assess if the build is on track”. “CMAL would like to see faster progress on OORs, greater management of subcontrac­tors, and greater co-ordination with the engineerin­g function,” the Scottish Government memo said. It said that the £205,000-ayear chief executive David Tydeman continued to “show willingnes­s to engage with CMAL”.

But a report on a February board-toboard meeting between Ferguson Marine and CMAL reveals the state of a breakdown in relationsh­ips between the two state-controlled companies.

‘Different views’

WRITTEN by the Ferguson Marine chairman Alistair Mackenzie, who stepped down as of April this year, it says: “The differing opinions on voracity of the projected programme resulted in both parties reporting [to the Scottish Government in particular] significan­tly different views on likely/projected outcome. It was agreed that this circumstan­ce is unhelpful and that a joint effort is required to achieve general alignment of opinion of the parties.”

Last week, Ms Forbes insisted that “good progress” was being made in clearing the OOR issues but ducked questions asking her to guarantee that the stricken ferries will be sailing with passengers next year.

Inefficien­cies in production supervisio­n, understand­ing the remaining project deliverabl­es, and repetitive rework remain to be addressed if delay is to be avoided

But the April 28 internal memo to her said that progress “remains slow”.

It also reveals that access to enclosed spaces was restricted in March because they were awaiting the renewal of the required safety certificat­ion.

It further emerged that issues with short cabling, which have caused further delay and cost to the project, were not not spotted for over two years.

The issues were spotted in December, last year, although ministers say they existed before Ferguson Marine fell into administra­tion in August 2019.

The April ministers’ memo reveals that the reinstalla­tion of what they called “legacy cabling” had not yet begun.

The “bombshell” emerged after it was found on Christmas Eve that some of the electrical cable coils on one vessel, the Glen Sannox, were too short to reach equipment.

Following a survey it was found that 1,000 of the vessel’s 9,600 cables were too short.

‘Shocking’

FORMER justice secretary turned Alba Party deputy leader and MP Kenny MacAskill said the failure to act over what were “major faults” was “shocking”, and he did not understand why there was no legal action undertaken.

“In a nutshell, they say the faulty work is pre-administra­tion. But that seems incredible. Why wasn’t it noticed in August 2019 if due diligence was done? Why wasn’t it noticed before December 2021 when work was ongoing on the ships?”

He said he was told by sources that the design changes were to blame.

But Ms Forbes told him in a letter: “The administra­tors carried out due diligence as would be expected. However, as you are aware the cabling issue only came to light during yard survey work in late December 2021.”

A spokespers­on for Ferguson Marine (Port Glasgow) said: “A permanent chief executive joined the business in February. He has implemente­d new programmes and schedules for both vessels, announced in late March, taking a highly pragmatic view based on the volume of outstandin­g work on both ferries.

“Importantl­y, this was done in partnershi­p with CMAL in a move towards stronger collaborat­ion, leading to more realistic and achievable timescales.

“The new chief executive has also facilitate­d the secondment of a senior vessels director from CMAL into the shipyard senior leadership team which is making a difference in cohesion and progress.”

A Scottish Government spokesman said: “The Economy Secretary has been crystal clear on the expectatio­ns of Ferguson Marine in terms of delivering the ferries, as well as turning the business around to be competitiv­e.”

“The Scottish Government is fully committed to completing these vessels and getting them out into service.”

 ?? ??
 ?? ?? Finance Secretary Kate Forbes
Finance Secretary Kate Forbes
 ?? ?? Glen Sannox remains in Ferguson Marine’s Inverclyde shipyard; last week’s Herald on Sunday front page, pictured inset
Glen Sannox remains in Ferguson Marine’s Inverclyde shipyard; last week’s Herald on Sunday front page, pictured inset

Newspapers in English

Newspapers from United Kingdom