The Oban Times

Time running out for 300 Dunbeg homes

-

DELAYS are putting pressure on a plan to build 300 houses in Dunbeg – before a deadline to spend £35 million of Scottish Government funding expires, councillor­s heard last week, writes Sandy Neil.

With time running short to complete the project before 2021, the council’s planning committee is seeking an earlier ‘special’ hearing to decide the applicatio­n in July during the recess.

Argyll and Bute Council was awarded £1.9 million from the Housing Infrastruc­ture Fund last November to upgrade Kirk Road in Dunbeg, but ‘some slippage’ in ‘the award timeline’ ‘delayed engagement with the preferred contractor, utilities companies and the council’.

Councillor­s on the planning and resources committee heard scrub clearance and tree felling had been completed, Scottish Water had begun work on the sewer and water main, and the council’s preferred contractor had signed the main contract finalising the Kirk Road programme of constructi­on, which is ‘likely’ to end in October 2018.

A report presented in the Kilmory chamber last Thursday continued: ‘Link Housing Associatio­n submitted a detailed planning consent for 300 new homes in April that will now be considered through the planning process and, if approved, will be accessed by the improved Kirk Road. It should also be noted that the Scottish Government has approved funding of £35 million to help deliver this housing developmen­t by 2021.’

The planning applicatio­n is due to be heard by the council’s planning committee in August but, owing to the tight deadline to finish the project before the government’s funding expires, councillor­s asked for a ‘special’ hearing, perhaps in July during the council’s recess.

The council’s head of governance and law, Charles Reppke, said: ‘It would be possible [to hold an earlier planning meeting], but you [councillor­s] would need to consider whether it was appropriat­e.’

Councillor Roddy McCuish said: ‘I’m worried. By August we’re getting near the winter and the worst time for building.’

The report also updated councillor­s on plans for a roundabout at the Halfway House filling station on the A85, which were approved in 2016, adding that the developer may also seek ‘to renew planning consent for the spa resort’.

A Dunbeg Working Group, which included the council, Link Group and Dunstaffna­ge Estate, agreed ‘the roundabout was very much a developmen­t all parties wish to see taken forward but that the principal barrier to constructi­on was funding’.

Newspapers in English

Newspapers from United Kingdom