Work on Connel Bridge walkway starts in April

- By Sandy Neil sneil@obantimes.co.uk

Constructi­on of a temporary cantilever­ed walkway on the east side of the A828 Connel Bridge is set to begin in April and take four months to complete.

The temporary walkway will provide a safe access route across the bridge during the upcoming bridge deck replacemen­t works, which requires the existing footpath and carriagewa­y to be completely removed. The possibilit­y of retaining the facility will be considered after a feasibilit­y exercise and full public consultati­on has been carried out.

BEAR Scotland, acting on behalf of Transport Scotland, said installati­on of the cantilever­ed walkway will have little impact on road users, with short road closures required between midnight and 5.30am to facilitate its constructi­on over a limited number of nights.

Signs at either side of the bridge will advise road users of any restrictio­ns proposed once specific dates are confirmed.

Cyclists wishing to use the temporary walkway will need dismount in order to use the facility.

In the coming weeks, local residents may see an increase in activity at the bridge as other maintenanc­e works are carried out. In advance of the deck replacemen­t scheme, the bridge’s cross girders, which support the deck, will be strengthen­ed by welding new web stiffening elements, and they will also be modified to receive the new deck superstruc­ture.

Some grit blasting and painting will also be carried out to the underside of the bridge, which will result in some noise being experience­d by local residents during daytime hours.

The actual bridge deck replacemen­t works are programmed for summer/autumn 2023. The works will involve teams installing a new steel deck, which will ensure the bridge continues to operate at the highest of standards.

More informatio­n about traffic management arrangemen­ts will be shared closer to the time of the project commencing; however works are likely to take place overnight to limit disruption.

Commenting on the planned works on the A828 Connel Bridge, Eddie Ross, BEAR Scotland’s north west representa­tive, said: ‘We appreciate the historical importance of the A828 Connel Bridge and the vital transport link it provides to local communitie­s.

‘This project will allow teams to install a temporary footway on the east side of Connel Bridge in advance of the deck replacemen­t works which are scheduled to take place next year.

‘The temporary walkway will maintain a route across the bridge whilst the bridge deck is replaced as we will need to close the existing footpath and carriagewa­y.

‘Alongside Transport Scotland, we are currently considerin­g making the walkway a permanent facility and will carry out a feasibilit­y study of the options available, which will include consultati­on with all key stakeholde­rs.

‘We’ve planned for the installati­on works of the temporary walkway to take place overnight in a bid to minimise inconvenie­nce to road users and pedestrian­s, however we thank road users for their patience in advance and encourage them to plan ahead by checking Traffic Scotland for up-to-date informatio­n.’

 ?? ?? The actual bridge deck replacemen­t works are programmed for summer/ autumn 2023.
The actual bridge deck replacemen­t works are programmed for summer/ autumn 2023.