The Press and Journal (Aberdeen and Aberdeenshire)

‘Very poor quality’ plans for offshore wind decom

- JEREMY CRESSWELL

More than 3.5GW of global offshore wind capacity will reach the end of operationa­l life by 2035 if no other action is taken – so says the UK’s Offshore Renewable Energy (ORE) Catapult.

Most of those turbines are in north-west Europe, primarily the North Sea, with the largest share being in UK waters. The average lifespan is 20-25 years.

ORE calculates that around 600 turbines will get the chop by 2030. Push on another five years, and EV extrapolat­ion seems to point to around 800-900 being removed by 2035.

It seems a lot, but it’s roughly equivalent to only two or three gas-fired or multi-fuel power stations such as Peterhead.

These numbers take no account of repowering, improvemen­ts in maintenanc­e and repair regimes or economic expediency.

In this regard, North Sea oil and gas sets an important precedent. A huge number of fields are now well past original expectatio­n, and there are many platforms which had a design life of 20-25 years, but which are now 40 years old or more.

And right now, expediency has thrown a spanner into the works of both industries because of Russia’s war with Ukraine. This has led to a dramatic rewrite of the global oil and gas supplies map, triggering an accelerati­on of the green energy push.

It is why the UK Government, for example, is resetting capacity targets and overhaulin­g the projects’ rule books for offshore wind, as are neighbours across the North Sea, and why it is pushing oil and gas operators to maximise production, regardless of global warming.

In the UK’s Offshore Wind Sector Deal published in March 2019, the prior target of 30GW was pushed to 40GW fixed turbines plus 1GW for floaters.

In April, the target was reset again to 50GW fixed and 5GW floaters.

DNV forecasts that the UK offshore wind industry will have around 19.5GW installed by mid-decade. That leaves only another five years to vastly more than double that capacity.

But, as the First and Second World Wars attest, it is remarkable what can be achieved in war-driven deep crisis.

EU neighbours have dramatical­ly ramped up their targets, too.

In February, the members of the European Parliament (MEPs) agreed under the EU Offshore Renewable Energy Strategy to set a 2030 target of at least 60GW and 300GW by 2050.

The EU also plans to develop at least 1GW of ocean energy and other emerging technologi­es by 2030, and 40GW by 2050.

In May, via the Esbjerg Declaratio­n, North Sea littoral states Belgium, Denmark, Germany and the Netherland­s agreed to jointly develop 150GW of new capacity in their waters by 2050, together with the creation of “energy islands” and export grid build-out.

They also strengthen­ed their commitment to offshore hydrogen and plan to build 30GW of electrolys­er capacity by 2030.

Then, in September, the EU refined and further reinforced its offshore energy targets.

Energy ministers linked to the North Seas Energy Cooperatio­n and the European Commission have pledged a “significan­t increase in their collective ambition”.

Nine have agreed to reach at least 260GW of offshore wind energy by 2050: Belgium, Denmark, France, Germany, Ireland, Luxembourg, the Netherland­s, Norway and Sweden.

This will represent more than 85% of the EU-wide ambition to reach 300GW by 2050 and is 17 times more than all of the EU’s current offshore wind capacity.

The nine also laid out intermedia­te targets of 76GW by 2030 and 193GW by 2040.

The numbers are huge and smell of political ambition driven by nearpanic.

When it comes to the latest commitment­s regarding offshore wind, there is the risk that the declaratio­ns may lead to significan­t over-build and therefore over-capacity resulting in mothballin­g and early decommissi­oning of far from life expired generating plants.

In the UK, there also is the risk that the contracts for difference system, which has over the past decade led to dramatic reductions in the cost of windfarms, especially offshore, will end up

The Scottish Government should not join a race to the bottom and instead would do better to make sure to deliver against their own priorities

strangling innovation, quality and safety. It will simply be the cheapest deal.

Expediency will take charge – and, in turn, this may have serious impacts on the drive to achieve a viable circular economy when it comes to offshore wind.

In theory, everything installed on the UK continenta­l shelf will have to be removed.

ORE Catapult has examined what it sees as the options ahead.

A cost-benefit analysis of five end-of-life scenarios was conducted for a representa­tive UK offshore wind farm of 35 turbines (6MW rating) reaching its 25-year operating life in 2040.

The scenarios were full removal, partial removal, full repowering, partial repowering and life extension.

ORE’s analysis shows that partial repowering with a 10MW turbine upgrade in a 210MW offshore wind farm site offers the highest net present value (NPV) of £221 million, extending the wind farm’s life for a further 25 years.

Life extension is the second-most economical­ly attractive option, with a £148m NPV having the lowest extra cost among all scenarios, but also preserving the same annual electricit­y production for a further 10 years.

Compared to partial

repowering, the cost of replacing foundation­s and cables reduces the return the developer or operator can expect from full repowering to £105m.

Total and partial decommissi­oning do not offer any wind farm revenue return to the developer or operator.

There is no mention of what the impacts on other sea users could be as a result of leaving infrastruc­ture partially in place. In that regard, the analysis displays partiality that favours the wind farm developer or operator.

ORE admits: “There is currently no standard legislatio­n to specify the best practices after operationa­l life ends, with decisions strongly

driven by the physical conditions, theoretica­lly admissible lifetimes of turbines, site conditions, country legislatio­n, logistical difficulti­es and environmen­tal impact.”

The catapult is currently developing an industrywi­de programme to cover not only the issues and understand­ing of what decommissi­oning will mean, but the wider circular economy impacts that component reuse and material recycling might have.

Its five-year Circular Economy for the Wind Sector Joint Industry Programme aims to bring together ideas and solutions from different researcher­s, operators, developers and

policymake­rs for the most sustainabl­e practices that can be adopted at the end of a wind farm’s operating life.

It is also developing the UK Floating Offshore Wind Centre of Excellence – although for why is a puzzle, as none of the wind floater technologi­es developed and built so far have happened here.

Dr Anne Velenturf, senior research fellow in circular economy at Leeds University, and who leads circular economy research for ORE, has strong views about what is presently not right about offshore wind, at least in the UK context.

She told EV: “It is very important for the wind industry to stay open and transparen­t, and to really deal with the sustainabi­lity challenges that they are facing.

“Credibilit­y and trust are easily lost and very difficult to regain, something fossil fuel companies know about.”

A couple of years ago, in a formal response to the Scottish Government’s consultati­on on decom, Velenturf warned: “A review of offshore wind decommissi­oning plans by our team at the University of Leeds revealed that the current guidance for the whole of the UK has resulted in very poor quality decommissi­oning plans (for offshore wind).”

In other words, the department for business, energy and industrial strategy is not doing its job properly.

Velenturf warned: “The Scottish Government should not join a race to the bottom and instead would do better to make sure to deliver against their own priorities in their National Performanc­e Framework.

“Decommissi­oning programmes should set out the extent of infrastruc­ture to be removed, methods and processes.

“They should include a base case of all infrastruc­ture being removed, alongside any alternativ­es that the operator proposes, backed up by evidence and reasoning for the preferred option.

“If we assume that the guidance has been more or less copied from the guidance provided by BEIS for the whole of the UK, then we can conclude that the guidance is unlikely to achieve any of these aspiration­s based on the general state of current decommissi­oning programmes that are publicly available.”

EV wonders whether this is also the case on the other side of the North Sea, or whether a more responsibl­e approach to offshore wind sustainabl­ility, let alone decom, is already ordained.

 ?? ?? WHAT LIES AHEAD? Researcher­s at ORE say the wind industry is facing sustainabi­lity challenges.
WHAT LIES AHEAD? Researcher­s at ORE say the wind industry is facing sustainabi­lity challenges.
 ?? ?? ORE’s Dr Anne Velenturf warns that the existing guidance for the breadth of the UK has resulted in inadequate decom plans for offshore wind.
ORE’s Dr Anne Velenturf warns that the existing guidance for the breadth of the UK has resulted in inadequate decom plans for offshore wind.

Newspapers in English

Newspapers from United Kingdom