The Press and Journal (Inverness, Highlands, and Islands)

Six-year delay in contract to train military pilots

-

A £3.2billion programme to contract out the training of military pilots is running almost six years behind schedule, the Whitehall spending watchdog has found.

Ascent – a consortium of LockheedMa­rtin and Babcock – was originally awarded the 25-year contract totrain aircrewfor the Ministry of Defence (MoD) in 2008 in amove intended to reduce costs and training times.

The scheme was scheduled to be running at full capacity by 2014, but the National Audit Office (NAO) said that a series of delays meant it would not now get there until the end of 2019. It found the early years of the contract were dogged by “significan­t concerns” about Ascent’s performanc­e but while the MoD has so far paid out more than £143million, it has only been able to claw back £308,000 in deductions for its failure to meet its responsibi­lities.

The NAO said the delays were in part due to the “substantia­l” cuts in the numbers of aircrew undergoing training, which had seen the value of the contract slashed from as much as £6.8billion to £3.2billion.

While Ascent’s performanc­e was considered to have improved since 2012 after the MoD raised its concerns with the shareholde­rs, theNAOsaid there was still “much to do” if it was to achieve the planned benefits of the contract.

The head of the NAO Amyas Morse said: “The department needs to understand better actual training performanc­e and what affects performanc­e before it can secure significan­t improvemen­ts from Ascent.

“Otherwise, there is a real risk thatmoving to the new training will affect the military’s ability to train the right number of aircrew at the right time.”

“Threre is a real risk the new training will military ability”

Newspapers in English

Newspapers from United Kingdom