The Press and Journal (Inverness, Highlands, and Islands)

Options to reconstruc­t road will cost millions

- ANDREW STEWART

Councillor­s on Orkney will consider options for the reconstruc­tion of the road on one of the Churchill Barriers when they meet next week.

Concerns about the surface of the road that runs along the top of the first Churchill Barrier have been doing the rounds for years.

It is believed that subsidence has caused warping of the road.

On Tuesday councillor­s on the developmen­t and infrastruc­ture committee will consider a report that sets out six possible options for reconstruc­ting the road

Most of these options include replacing the existing asphalt, but each of the options adds further steps at an increased cost. The options are: Replace the asphalt.

■ Replace the asphalt and include a reinforcin­g grid

■ As above and replace the existing sub-base material as well.

■ As above but also replace old tar-bound material.

■ Replace the asphalt including an asphalt reinforcin­g grid and replace the existing sub-base and old tar-bound material with a new sub-base wrapped in geotextile.

There’s also a sixth option, which is to do the minimum. This would mean only treating the worst of the cracking and failed patches or potholes in the road.

The report from council officers recommends exploring two of the options – the third and fourth.

The key difference between them is the replacemen­t of the old tar-bound material.

However, the report notes that this is “difficult to justify”.

The projected costs for these options would be £1.275 million and £2.285m respective­ly.

It is thought option three would leave the barrier in a better state for 20 years at half the cost of option four.

But the risk with it is that the area in worst condition, where investigat­ors found “excessive voiding”, might need additional maintenanc­e during those two decades.

The fact that the council is finally considerin­g these various options will come as a relief to many.

However, the plans are still at an early stage.

Councillor­s will not be making a decision on Tuesday over which option they want.

Rather, they will pick which ones should be looked at in greater detail before a final choice is made by the policy and resources committee.

These next steps will in themselves incur further costs.

The public have for years been raising concerns about the condition of the road on the first barrier – which links the Orkney Mainland to Lamb Holm.

In particular, those living on the isles linked to the Orkney Mainland by the four barriers have stressed the problems being seen with the road.

The council’s report refers to “defects in the form of longitudin­al cracking and surface undulation­s” that have been appearing.

Since 2017, investigat­ions have been undertaken by the local authority to identify the problem and see what could be done.

In 2019, a penetratin­g radar survey showed shadows that were thought to be voids deep within the barrier.

However, this was deemed inconclusi­ve without further investigat­ion being done.

Also in 2019, an advisory 40mph speed limit was introduced at the first barrier in an effort to keep motorists safe, particular­ly motorcycli­sts.

And in August last year, engineerin­g consultant Mott MacDonald was appointed to provide support and advice to the council.

The firm reviewed all the existing data and dug “trial pits” at the barrier. It found that there are indeed defects caused by the constructi­on and movement of the barrier.

 ?? ?? PROJECT: Orkney Islands Council is considerin­g its options for reconstruc­ting the first Churchill Barrier, which links Mainland and Lamb Holm.
PROJECT: Orkney Islands Council is considerin­g its options for reconstruc­ting the first Churchill Barrier, which links Mainland and Lamb Holm.

Newspapers in English

Newspapers from United Kingdom