The Railway Magazine

South West Main Line closed by major landslip

A structure weighing 12,600 tonnes that will carry the high speed route over the M42 motorway has been slid into place.

- By Chris Milner

THE four-track main line from London to Southampto­n, Bournemout­h and Exeter Central was closed from January 15, after a landslip on an embankment at Hook left the down slow line suspended in the air.

The slip also affected the down fast line, and led to a disruption of services between Farnboroug­h (Main) and Basingstok­e, leaving the Londonboun­d

lines unaffected.

The embankment, made of a mixture of London clay and other local soils, became saturated after days of heavy rain and a very wet winter. The slip was 44m long on a 10m high embankment, and is what engineers call a ‘rotational failure’.

Network Rail Wessex route director Mark Killick said at the time: “This is a huge landslip and is having a massive effect on customers. We’re still assessing the damage and it’s difficult to put a detailed timescale in place, but we know it’s going to be at least a week. We will need to stabilise the embankment, essentiall­y stopping it moving.”

In the interim, services from Weymouth, Southampto­n and Exeter were terminatin­g at Basingstok­e, with services from London ceasing at Farnboroug­h. A limited shuttle operation between Basingstok­e and Farnboroug­h using the up fast line was instigated, not calling at Hook, Winchfield and Fleet, while Waterloo-Basingstok­e stopping trains were cancelled.

Weekend repair work on January 21/22 aimed to permit the reinstatem­ent of limited services in the down direction from January 23 by severing the up fast either side of the slip, and slewing the down fast over to provide a track in each direction.

Network Rail said to complete repairs it would build an access road to bring in 9000 tonnes of rock and then insert steel piles to stabilise the embankment, but was unable to give a timescale for completion of the project.

HAVING been constructe­d alongside the motorway over the previous six months, HS2’s Marston Box bridge was moved 165m (180 yds) into position over the M42 during the Christmas holidays – a feat that HS2 Ltd believes to be the “world’s longest box slide”.

A team of around 450 people from constructi­on contractor Balfour Beatty VINCI (BBV) were involved in the operation, which took 40 hours to complete, at a speed of four metres (13ft) per hour.

Consisting of a base, three walls and a top slab, and developed by Mott MacDonald and Systra for BBV, the 86m (282ft) bridge, north of junction 9 on the motorway at Lea Marston in Warwickshi­re, will become part of a structure over double that length, carrying trains between Crewe and Birmingham Curzon Street.

Originally designed for constructi­on in a traditiona­l manner, the box slide technique was adopted in order to minimise disruption to road users. A sliding mechanism designed by Freyssinet pushed the bridge into place on a guiding raft.

Disruption

HS2 Ltd estimates that building a convention­al structure would have led to three months of overnight road closures and around two years of narrow lanes and speed restrictio­ns. Planned closures were reduced to around a fortnight in total – in December 2021 between Christmas and New Year for preparatio­n work, and again from December 24, 2022 until the early hours of January 3.

In fact, the bridge was installed and road reinstatem­ent completed 36 hours ahead of schedule, allowing the M42 to be reopened in both directions between junctions 9 and 10 on New Year’s Day.

 ?? GRAEME PICKERING ?? FIRST ‘777’ ENTERS SERVICE: After reaching agreement with unions over their operation, Stadler-built Class 777 No. 777049 became the first of the new Merseyrail fleet to enter service on January 23. The four-car unit made its public debut on the 10.50 Liverpool Central-Kirkby service and is seen shortly after arriving at its destinatio­n amid much interest from photograph­ers and local rail users. Units will initially be introduced on the Kirkby line, with all 53 of the trains, which are owned by the Liverpool City Region Combined Authority, expected to be in operation within the next 12 months – allowing the withdrawal of aged Class 507 and 508 EMUs.
GRAEME PICKERING FIRST ‘777’ ENTERS SERVICE: After reaching agreement with unions over their operation, Stadler-built Class 777 No. 777049 became the first of the new Merseyrail fleet to enter service on January 23. The four-car unit made its public debut on the 10.50 Liverpool Central-Kirkby service and is seen shortly after arriving at its destinatio­n amid much interest from photograph­ers and local rail users. Units will initially be introduced on the Kirkby line, with all 53 of the trains, which are owned by the Liverpool City Region Combined Authority, expected to be in operation within the next 12 months – allowing the withdrawal of aged Class 507 and 508 EMUs.
 ?? KEN BRUNT ?? Left: SWR EMU No. 450058 forms a Woking to Basingstok­e shuttle on January 18, running wrong line through Hook station which had been closed three days earlier due to the landslip on the down lines north of the station.
KEN BRUNT Left: SWR EMU No. 450058 forms a Woking to Basingstok­e shuttle on January 18, running wrong line through Hook station which had been closed three days earlier due to the landslip on the down lines north of the station.
 ?? NETWORK RAIL ?? Above: A close-up of the landslip on the embankment under the down slow line near Hook.
NETWORK RAIL Above: A close-up of the landslip on the embankment under the down slow line near Hook.
 ?? HS2 ?? The bridge is pictured in the process of being positioned over the M42 at Lea Marston, near Kingsbury in Warwickshi­re.
HS2 The bridge is pictured in the process of being positioned over the M42 at Lea Marston, near Kingsbury in Warwickshi­re.

Newspapers in English

Newspapers from United Kingdom