The Railway Magazine

Vale of Aylesbury viaduct unveiled

HS2 contractor EKFB has been busy on the northern outskirts of Aylesbury preparing the groundwork­s for the Thame Valley viaduct, which will carry the high-speed line at low level across the river’s floodplain.

- By Phil Marsh

MAIN constructi­on has begun on the 880 metre-long Thame Valley Viaduct to the north of Aylesbury.

The viaduct will have 36 spans, each formed of two 90 tonne precast box girders (beams) placed longitudin­ally on a series of 70 precast piers, which in turn each rest on three 45m-deep piles. The piers are only 3.3m above ground level, so this will be no Welwyn or Harringwor­th viaduct in appearance, despite the estimated total of nearly 6km (3¾ mile) of piling required.

32 spans are 25ms long and four are 20m, which when complete will have created the longest viaduct in what is known as the C23 Programme of HS2. This runs for 80km (50 miles) from just south of Beaconsfie­ld to Greatworth (south of Warwick), and will eventually boast 15 viaducts.

Off-site manufactur­e

The post-tensioned, precast box girders are manufactur­ed by Pacadar on the Isle of Grain in Kent using the same mould to ensure consistenc­y.

They are transporte­d individual­ly from there to site overnight by road.

Each end of the beam is labelled north or south. As there is no area on site large enough to turn one of the delivery lorries, the beams must be loaded the right way round in Kent for lifting off the trailer and onto the viaduct piers.

Once a beam has been lifted clear of the trailer by two crawler cranes, the lorry drives away and engineers check the beam’s dimensions the oldfashion­ed way by using a spirit level and tape measure. The beam is then lifted, swung and lowered onto the pre-prepared pier baseplates, each with four vertical bolts to secure them onto their designated pier, while 10 rods create a strong connection between the beams. A complete lift is carried out in about 15 minutes.

The viaduct’s deck, formed of reinforced concrete slab partly precast and partly created on-site, will be placed on the beams later for the rails to be installed upon.

The original plan was to have four precast beams, but a redesign halved this. As a result of this change benefits include environmen­tal, cost and flexibilit­y in the constructi­on sequence, plus a reduction in temporary works during constructi­on.

Just like Lego

Constructi­on of the piers began several months ago.

All the major elements of the bridge – the concrete piers, beams, reinforced concrete deck planks and parapet – are manufactur­ed off-site on the Isle of Grain and assembled on site, as HS2 puts it: “Like a giant Lego set!”

HS2 claims this is the first prefabrica­ted viaduct to be built in the UK.

Contractor EKFB is a joint venture between Effiage, Kier, Bam Nuttall and Ferrovial constructi­on, a Spanish company.

A spokespers­on said: “This structural design is based on similar viaducts built as part of the Spanish high-speed rail network, and reduces constructi­on time, workforce numbers, and embedded carbon.”

 ?? ALL PHOTOS TAKEN ON OCTOBER 30 BY PHIL MARSH ?? Two of the 72 beams in position, showing the height of the Thame Valley viaduct over the river’s floodplain.
ALL PHOTOS TAKEN ON OCTOBER 30 BY PHIL MARSH Two of the 72 beams in position, showing the height of the Thame Valley viaduct over the river’s floodplain.
 ?? ?? A 90 tonne beam arrives by road from the factory on the Isle of Grain.
A 90 tonne beam arrives by road from the factory on the Isle of Grain.
 ?? ?? Engineers check the beam’s dimensions and levels.
Engineers check the beam’s dimensions and levels.
 ?? ?? One of the viaduct’s pier foundation­s under constructi­on.
One of the viaduct’s pier foundation­s under constructi­on.

Newspapers in English

Newspapers from United Kingdom