The Scotsman

£45 million job fund is frozen after blunders by Scottish Government

- TOM PETERKIN

A FUND of over £45 million, supposed to go toward job creation has been frozen by the EU Commission because of problems with the Scottish Government’s system for managing the cash.

The EU Commission has suspended the money earmarked for Scotland under the European Social Fund after what it called “irregulari­ties” in spending.

The ESF provides cash for projects aimed at creating and supporting jobs in member states. The programmes funded by the cash focus mainly on in- creasing employment by support for unemployed, economical­ly inactive and disadvanta­ged people.

Problems with the Scottish government’s system for managing the funding were first highlighte­d last December.

Scottish ministers blamed a “technical issue” and said they were working to comply with EU regulation­s.

The money affected is from the ESF’S last funding round covering the period 2007-2013.

Payments of about 57.8 million euros (£41.4 million) due to go to projects in the Lowlands and Uplands and about 6.7 mil- lion euros (£4.8 million) for the Highlands and Islands have been suspended.

The EU Commission said it took the decision because it had not received sufficient assurances they had ironed out the issues from the Scottish Government.

Scottish officials first reported problems with their system for managing the money in December.

There followed eight months of talks between Edinburgh and Brussels, which failed to satisfy the Commission that enough had been done to sort out the problems.

The suspended funds represent around one quarter of the £193 million supposed to come to Scotland from the social fund between 2007 and 2013.

A EU Commission spokesman said: “Member states have the obligation to ensure that EU money is spent properly and that all procedures and documents respect the rules set out under the Structural Funds.

“In December 2014, the Scottish national authoritie­s reported problems in the management and control system within the managing authoritie­s (the Scottish Government).

“The control report from 2014 also found irregulari­ties concerning expenditur­e in several operations.

“On the basis of these findings and after an extensive dialogue with Scottish national authoritie­s during several months, the Commission decided that there is insufficie­nt assurance that all the measures to rectify the problems have been taken.”

The Commission said it would continue to work with the Scottish authoritie­s to resolve the situation.

Last night the Scottish Labour Public Services spokespers­on Jackie Baillie said: “This is hugely concerning news, especially given that this money goes to job opportunit­ies for vulnerable people.

“The Scottish Government needs to get to the bottom of what has gone wrong here; this is cash that should be supporting disadvanta­ged people that isn’t getting through.”

A Scottish Government spokesman said: “It is important to stress that no money will be lost to Scotland as a result of this process.

“Current interrupti­ons to programme payments were prompted by some public bodies failing to comply with their audit obligation­s – clearly this is unacceptab­le and is being addressed. Approvals for new programme payments are imminent but await final clearance by auditors. We are keen to ensure all processes fulfil EU regulation­s.

“Interrupti­ons with European programme funding due to technical issues are not uncommon.”

 ??  ??
 ??  ?? Jackie Baillie: This news is ‘hugely concerning’
Jackie Baillie: This news is ‘hugely concerning’

Newspapers in English