The Scotsman

Trams: Leith Walk facing longer closure

- By IAN SWANSON ian.swanson@edinburghn­ews.com

A long stretch of Leith Walk is to remain closed for an extra five months after the project to extend the tramline hit probems.

The council said some conflicts with undergroun­d pipes and cables along the route were more complex than expected, leading to delays in the completion of the work in some sections.

The section of Leith Walk from London Road to Crown Street is now expected to be completed by July 2022 instead of winter 2021/22.

But the council said the overall project, taking the trams from the current terminus at York Place all the way to Newhaven, remained on track for completion in spring 2023.

In an update to mark the twoyear point of the £207 million project, the council said 76 per cent of utility diversions had been completed and more than half the track laid.

But it said the programme for specific sections of the route had been affected by recent nationwide issues which had hit the entire constructi­on industry, including the impact of the Covid pandemic, shortages of constructi­on material and a lack of availabili­ty of skilled labourers.

"In addition, the project has come across utility conflicts at key junctions such as Jane Street, Bernard Street, Mcdonald Road and Tower Street that were more complex than expected and have impacted the completion date for certain sections.

“As a result, some stretches are scheduled to take longer than expected, including the Leith Walk section from London Road to Crown Street, which is now estimated to be completed by July 2022.”

The work work on the London Road to Crown Street section started in summer 2020.

The extension will add three

miles – with an extra eight stops – to the existing ninemile route from the Airport to York Place.

Transport convener Lesley Macinnes said: “We are making good progress towards the

delivery of Trams to Newhaven and many people have commented on the amount of track that has been laid so far.

“However, I do recognise the disruption this major project has caused to people

living and working nearby, and that changes to the programme, which are down to issues out with our control, are likely to affect them.”

 ?? ?? The Leith Walk section from London Road to Crown Street is set to be completed by July 2022
The Leith Walk section from London Road to Crown Street is set to be completed by July 2022

Newspapers in English

Newspapers from United Kingdom