The Sunday Telegraph

HS2 constructi­on ‘up to three years behind schedule’

- By Edward Malnick WHITEHALL EDITOR

CONSTRUCTI­ON of the controvers­ial HS2 rail line is up to three years behind schedule, campaigner­s have claimed.

The Sunday Telegraph can disclose that the firm behind the £56billion project has yet to begin work on large sections of the proposed track where building was initially due to start as early as 2016.

In one case, a water sports centre at a lake west of London has been told it will not have to vacate its site until 2019 or 2020 to allow the constructi­on of a viaduct, having previously been informed that work would begin in 2016.

Constructi­on of another section of the line in Warwickshi­re has been sus- pended until at least “late 2020”, with council officials stating that even that timetable is “subject to change”.

The cases are among a litany of examples collected by campaigner­s where the constructi­on of parts of the line, including bridges and tunnels, appears to be significan­tly behind a timetable submitted to Parliament in 2013 as part of the project’s environmen­tal statement, before MPs backed the line. It stated that the first phase of the route – between London and Birmingham – was due to open to passengers in 2026 – a claim HS2 maintains today.

The disclosure­s come amid a growing political row over the cost of the line. Last week The Telegraph disclosed that Andrea Leadsom, the leader of the Commons, told the Cabinet that HS2 represente­d poor value for money and the funding would be better spent elsewhere. Boris Johnson, the former foreign secretary, also called for the project to be scrapped.

HS2 Ltd insisted the 2013 timetable, submitted as part of a detailed report on the environmen­tal impact of the scheme, was only intended as an “indicative” schedule and had since been superseded by a “more detailed programme of works” which incorporat­ed changes requested by MPs and residents, but which it declined to release. It said work was under way on 60 sites between London and Birmingham.

Campaigner­s said the apparent inaction on many sites due for developmen­t by now under the 2013 schedule cast doubt on the insistence by HS2 Ltd and ministers that it was “on time”. Joe Rukin, campaign manager of Stop HS2, the pressure group, said: “HS2 is clearly three years late.”

“Advance works” on a major viaduct in the Colne Valley area of Hillingdon, west of London, have yet to be started, two years after they were due to begin.

Hillingdon Outdoor Activities Centre, which runs watersport­s on the lake that will be spanned by the viaduct, told members that it had been agreed that it would now only move in 2019 or 2020. It had originally been given until March 2018 to leave the site.

Separately, work on a bridge over the A46 in Kenilworth, Warwickshi­re, is now not due to begin until 2020, after the constructi­on of a roundabout. The 2013 timetable showed constructi­on of the bridge starting in the first quarter of 2018, to be completed by the second quarter of 2019.

Meanwhile, constructi­on on more than a dozen sections of line between South Ruislip and Ickenham, west of London, has yet to begin, 22 months on from the when the first works were originally due to have been completed.

An HS2 Ltd spokesman said: “The 2013 Environmen­tal Statement is not a programme of constructi­on works and to confuse the two is wrong and misleading. Following public consultati­on and Parliament­ary process, and the appointmen­t of early works contractor­s, the more detailed programme of works was developed. HS2 remains on track with constructi­on works well under way on 60 sites across the route.”

Newspapers in English

Newspapers from United Kingdom