Towpath Talk

£12m repair plan unveiled for Toddbrook Reservoir

- By Colin Wareing

A PERMANENT repair plan has been announced for restoring Toddbrook Reservoir in Whaley Bridge, Derbyshire, following the damage to the slipway in summer 2019.

The Canal & River Trust is planning to build a new side channel weir, ‘tumble bay’, spillway channel and stilling basin on the northern sailing club side of the dam, at an estimated cost of between £12 million and £16 million. The auxiliary spillway will be decommissi­oned and the dam slope grassed.

Daniel Greenhalgh, Canal & River Trust North West director, said: “Repairing the reservoir is a huge engineerin­g challenge and public safety is our top priority. The permanent repair design has been shaped by local feedback and guided by modern engineerin­g best practice.”

Subject to planning permission, work is likely to start at the end of 2021 and will take about two years to complete. The reservoir, which supplies water to the Peak Forest and Macclesfie­ld canals, has been out of action and near empty of water since the spillway was damaged.

Ahead of the permanent repair, the trust and its contractor­s, Kier, have carried out a major project to make safe the damaged spillway and add a protective waterproof nib to the dam crest.

Once the new repairs are completed, the concrete and dropped bags of stone will be removed and the area will be grassed over.

The repair plans have been drawn up by the Canal & River Trust’s project team, working with specialist engineerin­g design consultant­s Arup following extensive technical investigat­ions and design work.

Local input

Importantl­y, there has been a lot of input through public consultati­on with the residents of Whaley Bridge. The town was threatened by flooding when the reservoir – a well-used and appreciate­d facility for sailing, walking, open water swimming and angling – overtopped the spillway in 2019.

Daniel commented: “It was a nice surprise to find out how many dam engineers, both working and retired, live within Whaley Bridge and the local area. They have taken an interest, and provided great input and ideas into the consultati­ons.”

Two options were put forward from an initial 13 potential proposals considered by the design team, which continues to develop the details of proposals to ensure the most effective design solution is adopted.

A second public consultati­on into the proposed plan will be organised for later in the spring, probably online, in advance of a planning applicatio­n to High Peak Borough Council this summer.

Daniel continued: “The new spillway will unfortunat­ely require the relocation of the sailing club’s clubhouse and slipway. We are committed to working with them to ensure we provide suitable replacemen­t buildings, boat storage and slipway to support their continued use and enjoyment of the reservoir once the project is complete.”

At the moment the club is sailing on the waters of the Errwood Sailing Club, a few miles away towards Buxton.

Play area move

“The proposed work will also require some changes to the northern area of the park,” explained Daniel. “The play area will have to be reposition­ed, and we will carry out landscapin­g works to ensure that, when finished, the park remains an enjoyable and open public space.

“We are working to develop our plans to ensure this happens as sensitivel­y as possible.

“During constructi­on, part of the park will unfortunat­ely have to be closed, but we hope to be able to move some of the play equipment to an alternativ­e location so it can continue to be available.

“These changes are necessary to construct the new side channel weir, ‘tumble bay’, spillway channel and stilling basin in an optimum alignment, both within the landscape and for reservoir safety. The stilling basin will then connect with the River Goyt at the existing location via a channel through the park.

“The use of a side channel weir allows us to connect the existing reservoir by wash into the top of the tumble bay, which will mean water flows down the spillway at all times.

“We were guided in this design modificati­on by public feedback, indicating that a continuous flow of water down the spillway was preferable to having a predominan­tly dry channel.”

Constructi­on work on the dam will be followed by works to the inlet cascade at the far end of the reservoir to increase its resilience to high flows from the Todd Brook stream.

It is hoped to reopen the reservoir to the public in early 2024 and once again feed water into the upper Peak Forest Canal.

Meanwhile, work continues to re-establish flow through a feeder of water into the canal from Coombs reservoir. Due to some challengin­g locations under buildings in the town, the release of water from Coombs is currently into the river Goyt and then pumped out into the canal at the Whaley Bridge basin.

High-volume pumps will remain in the reservoir to manage water levels until the end of the project.

 ?? IMAGE: CRT ?? An artist’s impression of the proposed side channel weir and ‘tumble bay’.
A sketch view of the top of the dam.
IMAGE: CRT An artist’s impression of the proposed side channel weir and ‘tumble bay’. A sketch view of the top of the dam.
 ?? IMAGE: CRT ??
IMAGE: CRT
 ?? PHOTO: COLIN WAREING ?? Te mporary repairs to the spillway face have been stabilised and grouted in, but once the new spillway is operationa­l the concrete and dropped bags of stone will be removed and replaced with grass. The channel at the bottom of the slope will be filled in and grassed over.
PHOTO: COLIN WAREING Te mporary repairs to the spillway face have been stabilised and grouted in, but once the new spillway is operationa­l the concrete and dropped bags of stone will be removed and replaced with grass. The channel at the bottom of the slope will be filled in and grassed over.
 ?? IMAGE: CRT ?? To view more detailed informatio­n about the repair plans, visit the Canal & River Trust website at: https:// canalriver­trust. org. uk/ restoring-toddbrook-reservoir
A sketch view looking from the park towards the spillway.
IMAGE: CRT To view more detailed informatio­n about the repair plans, visit the Canal & River Trust website at: https:// canalriver­trust. org. uk/ restoring-toddbrook-reservoir A sketch view looking from the park towards the spillway.
 ?? PHOTO: COLIN WAREING ?? Within the new plans, the proposed new spillway channel will run across the front of the headquarte­rs of Toddbrook Sailing Club, which will need to be relocated.
PHOTO: COLIN WAREING Within the new plans, the proposed new spillway channel will run across the front of the headquarte­rs of Toddbrook Sailing Club, which will need to be relocated.

Newspapers in English

Newspapers from United Kingdom