Work on a £21.6million rebuild of a West Sussex college is progressing.
Work on the Woodlands Meed college in Burgess Hill began at the end of last year. The contractor ISG has now completed the sheet piling work and the equipment has now left the site. Storm drainage works have begun which will safely control the run off of surface water from the new college.
The groundwork is continuing to prepare the site ahead of the main construction commencing in the summer.
A ground-breaking celebration is planned for the spring.