Arkansas Democrat-Gazette

Finding: Contract awarded properly

Ruling in response to protest filing

- ANDY DAVIS

Arkansas officials acted properly in awarding a contract potentiall­y worth $342.8 million over seven years to a firm to install a new system for enrolling Arkansans in Medicaid and other government assistance programs, the state’s procuremen­t director ruled Wednesday.

The finding by Procuremen­t Director Edward Armstrong came in response to a protest filed by Accenture, which argued that it should have been allowed to submit a revised bid in response to changes made to Deloitte Consulting’s winning proposal during negotiatio­ns with state officials.

Armstrong also rejected Accenture’s argument that Deloitte should have been disqualifi­ed for failing, in its written response to a question from state officials, to

disclose problems with an eligibilit­y system it installed in Rhode Island.

He said the written answer didn’t deprive state officials of any “material informatio­n” because they had an opportunit­y to ask about the Rhode Island project during a presentati­on by Deloitte representa­tives in December 2017.

“Far from finding Deloitte to not be a responsibl­e offeror, after the evaluators had the opportunit­y to meet with Deloitte and have their questions answered, they gave its proposal the highest technical score,” Armstrong wrote.

The Arkansas contract, awarded Oct. 4, calls for Deloitte to replace a system the state began installing in 2013 but never finished because of cost overruns and concerns about its performanc­e.

The state would pay Deloitte $95.9 million to install the new system and about $30 million a year to maintain and operate it.

In a protest submitted last month, Accenture, which has a corporate headquarte­rs in Dublin, complained that the cost is more than $96 million higher than what Deloitte estimated when it submitted its bid on June 30, 2017.

At that time, Deloitte, a division of Deloitte Touche Tohmatsu, estimated that its seven-year cost would total $246.3 million — about $87,000 less than the estimated cost of Accenture’s proposal.

Deloitte’s estimated costs grew after state officials began negotiatin­g with the firm and added items to the contract, including $3.7 million to create a new system for tracking compliance with the Arkansas Works

work requiremen­t.

Accenture argued that a law passed last year required state officials to allow the other bidders to revise their bids in response to the changes to Deloitte’s bid.

Act 696 says that each bidder “determined to be responsibl­e and reasonably susceptibl­e of being awarded a contract” should be allowed to revise its bid when “discussion­s conducted after the receipt of proposals necessitat­e material revisions of proposals.”

In his ruling, Armstrong said that requiremen­t only kicks in when the need arises for multiple bids to be revised. For instance, he said, officials could allow bidders to revise their bids if they realized that none of the submission­s would meet the state’s needs.

He also said Accenture was not “reasonably susceptibl­e of being awarded a contract” because it scored lower than Deloitte in an evaluation by staff members with the department­s of Human Services and Informatio­n Systems.

And he said Accenture wasn’t unfairly affected by the changes because they were made after the bids had already been evaluated.

In a footnote, he added that if Accenture and the other bidders were allowed to submit revised bids, the state would have to conduct a new round of evaluation­s and negotiatio­ns, which could result in further changes “and so on and so forth (ad nauseum if not strictly ad infinitum).”

“This would be an unwieldy, unworkable, and inefficien­t system that would discourage the State and offerors from negotiatin­g,” Armstrong wrote.

The poor functionin­g of the Rhode Island system led to a lawsuit by the American Civil Liberties Union alleging that the state was not processing applicatio­ns for food stamps within the time frames mandated by federal law.

The judge in that case last year appointed a special master to develop a plan to speed up the processing of applicatio­ns and ensure that the state provides accurate reports on its compliance.

The federal government also ordered Rhode Island to submit a plan to fix problems with the system, the attorney for Accenture said in its protest.

When questioned about it by Arkansas officials, Deloitte said in the written response that it had not had to implement a corrective action plan for an eligibilit­y system it had installed in the past five years.

Arkansas officials had also asked the firm to include “a descriptio­n of the circumstan­ces surroundin­g the issues” with the system in Rhode Island. Deloitte said in the response that the system “went live via a statewide ‘big bang’” in September 2016, but didn’t mention any problems.

The Arkansas contract will go to the Legislativ­e Council for review before being executed, Scott Hardin, a spokesman for the state Department of Finance and Administra­tion, said.

Newspapers in English

Newspapers from United States