City: Tunnel's flaws limit flood protection

Austin wants $22.3M back from constructi­on firm, which is suing city.

- By Elizabeth Findell efindell@statesman.com

Poor-quality concrete. No tunnel liner. Missing rebar. A “patchwork of repairs.”

After more than $161 million spent, the new Waller Creek Tunnel has severe structural problems that will reduce its ability to control flooding in downtown Austin and lessen the tunnel’s lifespan, an attorney representi­ng the city said in a letter to a contractor last month.

“This impacts the entire purpose of the tunnel,” the Feb. 23 letter said.

The city said S.J. Louis Constructi­on, the tunnel’s primary builder, didn’t follow design specificat­ions and instead built a shoddy tunnel with concrete and liner problems and with missing sections of rebar needed for structural integrity. Because of that, the Waller Creek project has lost much of its “freeboard” — essentiall­y, its extra capacity built in to guard against unexpected­ly large floods.

“The loss of freeboard reduces the primary purpose of the tunnel, flood protection,” the city wrote in the letter. “The City will never be made whole and is forced to accept a tunnel with a diminished value.”

Austin would like $22.3 million back from S.J. Louis.

The firm instead sued the city this week.

The Waller Creek Tunnel, under constructi­on from the southern side of Waterloo Park since 2011, is a 1-mile channel to Lady Bird Lake designed to protect nearby areas from flooding and allow developmen­t of a major portion of downtown that is currently in

the flood plain. The project has been beset with delays and cost increases.

How badly might the struc- tural issues affect flood con-

trol? The city won’t say. City spokespeop­le issued

a short statement calling the tunnel “a critical piece of our flood protection infrastruc­ture” but refused to answer any questions, including what its capacity is believed to be now, whether the problems could

affect redevelopm­ent in the area and what the impact could be in case of a 100-year flood. The defects have already

caused delays and required repairs, the city’s letter said.

In 2013 and 2014, Austin hired a forensic engineerin­g firm to find out how bad the tunnel’s problems were and “discovered that the scope of defects was greater than originally thought,” according to the letter.

S.J. Louis’s portion of the job was technicall­y completed in 2015, and the firm continued to make repairs until last year, the letter said. But even with the repairs, the tunnel’s structural integrity

and lifespan remain diminished, according to the city.

The Feb. 23 letter demanded S.J. Louis repay Austin $22.3 million for a 10percentr­educed value of the tunnel, delays in

completing itand costs to determine the extent of the constructi­on flaws. Without payment, Austin would terminate the firm’s $48 million contract, which has been paid, minus $1.5 million held in retainage. Instead, S.J. Louis filed

suit this week. The city can’t terminate a contract that’s already complete, the firm argued, saying that Austin

confirmed work was finished in 2015. It called the city’s threat to retroactiv­ely terminate it a way to gain leverage to receive payment.

“The steps being taken by the City are repugnant to the concepts of fair dealing,” the suit says. “Terminatio­n of the Contract would devastate S.J. Louis’s business

because it is required to disclose terminatio­n in future applicatio­n for government/ public works contracts.” The firm asked for a tem

porary restrainin­g order to prevent Austin from terminatin­g the contract. Its representa­tives could not immedi

ately be reached Wednesday. The dispute with S.J. Louis is separate from the other

high-profile issue with the Waller Creek Tunnel: City officials realized in 2014 that the intake building in Waterloo Park, where water enters the tunnel and filters pull out

debris, blocked a protected sightline of the Capitol. The facility was about 16 feet too tall, so pieces of the partly constructe­d building were demolished and a redesign began.

The extra constructi­on work and related delays forced t he city to pay intake facility contractor Oscar Renda Contractin­g

about $5 million extra. The city has said it would try to recoup those costs from the two engineerin­g firms that

designed the tunnel system, Espey Consultant­s and Kellogg Brown and Root.

The cost of the project rose from $25 million when voters first approved it in 1998, to $68.3 million when the city asked Travis County

for funding help in 2006, to $150 million in 2014 and then to $161 million in 2016,

whenthe city addedmoney to cover design flaws.

 ?? JAY JANNER / AMERICAN-STATESMAN ?? The city has accused a constructi­on firm of shoddy work on the Waller Creek Tunnel. The firm filed suit this week, saying the city can’t terminate a contract that’s already complete.
JAY JANNER / AMERICAN-STATESMAN The city has accused a constructi­on firm of shoddy work on the Waller Creek Tunnel. The firm filed suit this week, saying the city can’t terminate a contract that’s already complete.
 ?? CONTRIBUTE­D BY THE CITY OF AUSTIN ?? Crews with S.J. Louis Constructi­on chip out and replace patches of concrete a few years ago in the Waller Creek Tunnel to reinforce areas where the concrete wasn’t strong enough.
CONTRIBUTE­D BY THE CITY OF AUSTIN Crews with S.J. Louis Constructi­on chip out and replace patches of concrete a few years ago in the Waller Creek Tunnel to reinforce areas where the concrete wasn’t strong enough.