Baltimore Sun

Residents press for informatio­n

-

The Nov. 26 collapse followed another in 2014, when a separate stretch of East 26th Street two blocks west fully collapsed into the CSX Transporta­tion railroad tracks below, taking parked cars and other parts of the street with it. That collapse displaced about 20 families for more than a month and prompted a year-long constructi­on project to replace the retaining wall.

The more recent collapse was far less dramatic than the one in 2014, and no residents have been evacuated or displaced. However, it raised questions among local residents like Larry, who doubt the inspection­s have occurred as promised.

“How do we know that they’re really monitoring it?” Larry said.

The city has provided few answers.

In a statement Monday, transporta­tion department spokesman German Vigil said that, since 2014, the department “has had improved communicat­ion with CSX” and officials “have continued to meet and discuss maintenanc­e and responsibi­lities” for portions of the roadway that abut the CSX-owned train tracks.

“Our main priority is to safeguard the community and the rail line by stabilizin­g this section of wall so that a new structure can be built,” Vigil said.

He said the city has not discussed with CSX who would pay for the repairs. The city and the railroad split the cost of repairs after the 2014 collapse.

CSX, which restarted train traffic through the area within hours of the latest collapse, has said it is working with the city.

However, neither the city transporta­tion department nor Mayor Catherine Pugh’s office has responded to a list of questions and document requests from The Sun, including for records of any inspection­s of the street that have occurred in recent years.

Vigil said the city determined the section of the street that collapsed last week was safe in the 1990s, when it replaced another portion of the retaining wall on the block. And he said it used ground-penetratin­g radar to assess the street again after the 2014 collapse. But he did not have any records to immediatel­y share from either assessment, as those documents were being reviewed by the city.

He said the city did not have any reason to believe that recent undergroun­d utility work in the area had contribute­d to the collapse last week.

Pugh said at the site last week that it was “probably going to be a number of days” before the repairs were completed.

A week later, constructi­on at the scene appeared nowhere near completion.

Vigil said Monday the wall had been stabilized and the damaged section removed.

Along the block in question, there is a short retaining wall along the railroad tracks, and then another one several feet back that is larger and meets the street above. It was that second, larger retaining wall that was compromise­d last week.

By Monday afternoon, crews had cleared away the damaged portion of the retaining wall — about half the length of the block — and draped large pieces of white plastic over the otherwise exposed earth beneath East 26th Street.

An excavator on the street was digging out dirt between the shorter retaining wall near the tracks and the covered earth wall — likely in preparatio­n to construct a new wall to replace the one that collapsed and was removed.

About 1 p.m. Monday, a large piece of drilling machinery was delivered to the site. It was similar to the machinery used in 2014 to install a temporary retaining wall with steel pilings along the stretch of roadway that collapsed that year, stabilizin­g the street while a more permanent, cement retaining wall was installed.

It was unclear whether the city would be taking a similar approach to shoring up the street this time around.

Cross said he talked to the mayor twice last week, and she assured him that she was taking the matter seriously.

“She just said that we need to work on a comprehens­ive strategy,” he said. “She didn’t want this to be piecemeal.”

Then- Mayor Stephanie RawlingsBl­ake’s administra­tion sent a similar message to the community after the 2014 collapse, and Cross said he wishes the city had “better and more consistent communicat­ion” and followed through on its promises.

Instead, “it’s always just damage control,” he said. “It’s always just quickly saying things to people in the moment to get them to calm down.”

Larry said he had one conversati­on with liaisons from the city last week, but they only told him “in very vague ways what was going on” and did not provide many answers to his questions. He hasn’t been briefed since, he said — even as the constructi­on work continued outside his window.

The lack of informatio­n from the city has to stop, he said.

“There’s a large group of us in the neighborho­od who are banding together,” he said. “We’re doing a full-court press here to get some answers.”

 ?? JERRY JACKSON/BALTIMORE SUN ?? Contractor­s continue to work on the site along 26th Street where an aging retaining wall buckled above the CSX tracks last week.
JERRY JACKSON/BALTIMORE SUN Contractor­s continue to work on the site along 26th Street where an aging retaining wall buckled above the CSX tracks last week.

Newspapers in English

Newspapers from United States