Boston Herald

OVER BUDGET, BEHIND SCHEDULE

Report reveals costly, sluggish MBTA fare-collection overhaul

- By Gayla Cawley gcawley@bostonhera­ld.com

A new report by a Boston-based think tank has found that the MBTA’s farecollec­tion overhaul project is $211 million over budget and now approaches $1B cost while running three years behind schedule.

“One takeaway that we have is that this mega project approachin­g $1 billion went off the rails originally, and the new MBTA (general) manager, Steve Poftak, basically took extreme steps to correct the problems,” said Greg Sullivan, co-author of the report released by Pioneer Institute on Thursday.

“We’re concluding that this project is back on track and it’s being successful­ly implemente­d day by day.”

The report examines the difficulti­es the agency encountere­d with its initial $723 million contract for the project, which seeks to modernize the T’s fare-collection system.

MBTA spokespers­on Joe Pesaturo said T riders “will benefit greatly from the new tap-and-go system, which will allow them to pay fares by using phones, contactles­s credit cards, or the new CharlieCar­ds on all subway lines and bus routes.”

In February 2019, the MBTA sent a breach-ofcontract letter to Boston AFC 2.0 OpCo LLC, the corporatio­n tasked with completing and operating the system, but rescinded it a few months later and instead opted to renegotiat­e the March 2018 deal, the report found.

Jim Stergios, executive director of the Pioneer Institute, said this put taxpayers “on the hook for an additional $211 million.”

The new contract, signed in June 2020, increased its cost from $723 million to $934 million, and delayed full implementa­tion by three years — from May 2021 to May 2024.

“The original contract, in hindsight, was a catastroph­e because it was completely unrealisti­c to expect this system to be designed and operated in less than two years,” said Sullivan.

The new contract calls for a phased approach to implementa­tion, rather than launching the new system across all stations at one time. The T said it determined the initial approach — which resulted in a compressed timeline for testing, installati­on, and customer transition — was not feasible.

The revised deal also “includes a robust risk allocation with substantia­l financial consequenc­es and incentives around timeliness and delivery,” Pesaturo said.

“That agreement is the result of negotiatio­ns which addressed both the risks the MBTA faced in the original agreement, and the underlying concerns the MBTA had at the time about OpCo’s performanc­e,” said Pesaturo. “If OpCo does prove to be delayed in completing the project, the price of the project will be reduced by every day of such a delay.”

 ?? STUART CAHILL / HERALD STAFF ?? SHINY NEW TOYS: The newer Charlie Card machines at the Red Line Charles/MGH station on Wednesday. The machine overhaul project is $211 million over budget and three years behind schedule, according to a Pioneer Institute report.
STUART CAHILL / HERALD STAFF SHINY NEW TOYS: The newer Charlie Card machines at the Red Line Charles/MGH station on Wednesday. The machine overhaul project is $211 million over budget and three years behind schedule, according to a Pioneer Institute report.

Newspapers in English

Newspapers from United States