Chattanooga Times Free Press

Laying a foundation

Concrete steps in place for replacemen­t lock at Chickamaug­a

- BY DAVE FLESSNER STAFF WRITER

For the second time since work began on building a replacemen­t lock at the Chickamaug­a Dam in Chattanoog­a 12 years ago, a concrete batch plant has been erected along the Tennessee River to produce the tons of concrete needed to build the new chamber walls for a new and larger lock.

After heavy rains delayed work on the $758 million lock replacemen­t project this winter, AECom contractor­s are again busy preparing a conveyor system to transport the concrete into the giant 600-foot-by-110-foot lock chamber

erected next to the existing smaller lock which is suffering from “concrete growth” in its aggregate makeup.

“You should soon start seeing some tower cranes put on the site in the next couple of months to help bring some large pieces in place for the constructi­on of the concrete chamber walls,” said Lt. Col. Cullen Jones, commander of the Nashville district of the Army Corps of Engineers. “The heavy rains did stall some of our work for a few weeks, but the good news is that we are now working with AECom [the contractor for the next $240 million phase of the project] to identify both risks and opportunit­ies to help us get this project done quicker, on budget and with high quality.”

Jones said some equipment used

“You should soon start seeing some tower cranes put on the site in the next couple of months to help bring some large pieces in place for the constructi­on of the concrete chamber walls.” –

LT. COL. CULLEN JONES, COMMANDER OF THE NASHVILLE DISTRICT OF THE ARMY CORPS OF ENGINEERS

by the Corps at the Olmsted Lock and Dam on the Ohio River was brought to the Chickamaug­a lock project to help expedite the work.

Adam Walker, project manager for the Chickamaug­a lock, said a 1,000foot conveyor system to bring the concrete from the batch plant to the lock site should be in place and in operation by this summer.

“There will be three tower cranes on site — two within the coffer dam and one on the land side — to get all the equipment in the chamber and support the building of the concrete walls,” he said.

The replacemen­t lock project, one of Chattanoog­a’s biggest constructi­on projects, is designed to improve river transporta­tion and flow on the upper third of the Tennessee River by allowing riverboats to lock through the Chickamaug­a lock with multiple barges at one time. Currently, boat operators have to move each barge separately through the smaller, existing lock, which was built nearly 80 years ago.

Within the new lock being built beneath the dam, a major excavation project was completed just before record rainfalls forced the Tennessee Valley Authority to open up most of the spillways at the Chickamaug­a Dam and raise the Tennessee River by 12 feet above its normal level for nearly a month.

Heeter GeoTechnic­al, which completed its excavation work Feb. 1, dug down as much as 35 feet in the river bottom to remove more than 100,000 cubic yards of rock to prepare the lock site beneath the dam.

The higher river and heavy rain filled the coffer dam.

The rains are the latest delay in the Chickamaug­a lock replacemen­t efforts by the Corps of Engineers, which began a decade and a half ago and, due to funding delays and constructi­on complicati­ons, has more than doubled in cost. Walker said the Corps has already spent more than $250 million on site preparatio­n, road rerouting and constructi­on of the coffer dam.

Contractor­s for the Corps previously erected a batch concrete plant near the lock project, but that plant was later relocated when funding from Congress for the Chickamaug­a lock stalled and most of the money available for new locks and dams was spent for the Olmsted lock and dam in Ohio.

In the current fiscal year, the Corps has allocated $89.7 million for the Chickamaug­a project so the Corps exercised four more options on the next phases of the project in late March, Walker said.

Although no money for the Chickamaug­a lock was included in President Donald Trump’s original budget plan a year ago, Congress ultimately allocated the extra funding for the Chickamaug­a lock this year, and the Corps estimates funding next year for the replacemen­t lock at Chickamaug­a could be as much as $104.3 million.

President Trump redirected $1 billion from the Corps of Engineers budget last month for border security along the Mexican-U.S. border under his emergency declaratio­n. But the Inland Waterways Users Fund, which is jointly funded by taxpayers and the barge industry through diesel taxes and is used to fund projects like the Chickmauga Lock, was not affected by the redirectio­n of funds under Trump’s emergency order.

“None of the U.S. Army Corps of Engineers’ Civil Works appropriat­ions have been redirected for border barrier purposes,” Gene Pawlik, a public affairs officer for the U.S. Army Corps of Engineers in Washington, D.C., said Tuesday.

With adequate funding, the new Chickamaug­a lock could be finished by 2024, Jones said.

 ?? STAFF FILE PHOTO ?? A door of the functionin­g lock is seen at the Chickamaug­a Dam.
STAFF FILE PHOTO A door of the functionin­g lock is seen at the Chickamaug­a Dam.

Newspapers in English

Newspapers from United States