Chattanooga Times Free Press

Funding locks up at Chickamaug­a

Corps reassesses costs and schedule for lock replacemen­t

- BY DAVE FLESSNER STAFF WRITER

Chattanoog­a’s biggest constructi­on project is continuing on the Tennessee River even though no new funding is being provided this year for the halfbuilt endeavor.

The U.S. Army Corps of Engineers, which is building the new and bigger lock through the Chickamaug­a Dam to handle more river barge traffic, provided no funds for the replacemen­t lock in Chattanoog­a in its 2023 work plan despite increases in overall funding for infrastruc­ture projects this year.

In President Joe Biden’s initial budget plan, the Chickamaug­a Lock was proposed to get $39.3 million in fiscal 2023 to fund the project to its completion, according to the Waterways Journal Weekly. But the Corps’ final work plan released last month provided no new funds for Chickamaug­a this year.

Deb Calhoun, senior vice president for the barge industry group Waterways Council Inc., said in a statement Wednesday the industry was disappoint­ed.

“Chickamaug­a Lock, like many projects, is facing challenges, but we look forward to it becoming operationa­l in 2026,” she said.

After receiving a record $191 million in funding for the new Chickamaug­a Lock two years ago, constructi­on of a new lock at the Chickamaug­a Dam has continued by the contractor for the project, the Oakland, California-based Shimmick Constructi­on Co.

But additional funding to Chickamaug­a was suspended when the Corps determined it no longer had the capability to execute more funding on the project this year and is reassessin­g its cost and completion schedule.

Kevin Jasper, chief of the integrated project office at the Nashville district office for the U.S. Army Corps of Engineers, said no new contracts will be awarded for the Chickamaug­a Lock work in 2023 and contracts for the remaining work on the downstream approach wall and the decommissi­oning of the existing lock will be awarded in 2024-25.

“The lack of funding this year will not impact ongoing work on the replacemen­t lock,” he said in an emailed statement.

Jasper estimates the completion of the new Chickamaug­a Lock may now take until 2028 or 2029, which is two to three years later than what the Corps had previously projected.

During an August 2022 meeting of the Corps with the Inland Waterways Users Board, Stephanie Hall, deputy district engineer for the Nashville engineerin­g district, said work on the Chickamaug­a Lock contract was 42% complete. Hall said the contractor was experienci­ng delays due to supply chain interrupti­ons and other pandemic-related problems.

Shimmick continues to work to build the concrete walls and floors of the new 110-by-600-foot lock beneath the Chickamaug­a Dam on the Tennessee River. Last year, the contractor requested an additional $96.3 million and 590 days to complete its work, Hall said.

The new lock will replace the smaller and crumbling existing lock originally built by the Tennessee Valley Authority in 1940. The bigger lock will be able to handle up to nine jumbo barges at one time, while the current lock can only have one such barge at a time.

Lt. Gen. Scott Spellmon, the chief of engineers and commanding general, has said the bigger lock will help accommodat­e more and faster shipments of goods on America’s inland waterways, one of the most efficient means of transporti­ng heavy commoditie­s and equipment. The Corps projects that the lock helps keep up to 150,000 trucks off Interstate 75 and lowers the transporta­tion costs for many companies, including Olin Corp. in Cleveland, Tennessee, and A.E. Staley in Loudon.

The new lock is also needed to replace the 80-year-old existing passageway through the Chickamaug­a Dam, which suffers from “concrete growth” due to the alkali aggregate reactions present in the concrete since the existing lock’s original constructi­on.

The Corps is now engaged in an alternativ­e dispute resolution process on the costs and schedule of the project with Shimmick. In the meantime, the Corps is updating its costs and schedule for the Chickamaug­a Lock program, which should be released later this spring, according to Corps spokesman Bill Peoples.

Last year, Chickamaug­a handled 2,493 lockages, Peoples said.

 ?? STAFF PHOTO BY ROBIN RUDD ?? Work continues last August on the Chickamaug­a Dam Lock replacemen­t.
STAFF PHOTO BY ROBIN RUDD Work continues last August on the Chickamaug­a Dam Lock replacemen­t.

Newspapers in English

Newspapers from United States