Court filing: General Iron could have stayed in Lincoln Park, but city pushed move despite federal probe

- BY BRETT CHASE, STAFF REPORTER bchase@suntimes.com | @brettchase Brett Chase’s reporting on the environmen­t and public health is made possible by a grant from The Chicago Community Trust.

General Iron could have continued operating on the North Side while Mayor Lori Lightfoot’s administra­tion responded to a federal civil rights investigat­ion that launched last fall, a lawyer for the car shredder’s owner said in a court filing Thursday.

Reserve Management Group, which is suing the city over a stalled permit to operate the relocated and rebranded scrap metal shredding operation that is already built on the Southeast Side, referred to a two-page agreement that the city signed with the company in September 2019.

That document laid out a plan for General Iron to close its longtime Lincoln Park operation at the end of 2020 so the company could move to East 116th Street along the Calumet River by the spring of this year, provided it won an operating permit. In a filing in federal court in Chicago, RMG said it “has complied with the Agreement to its substantia­l detriment.”

But last October, the U.S. Department of Housing and Urban Developmen­t opened a civil rights investigat­ion into city zoning and land-use practices. At that time, the city had a chance to tell RMG that there would be a delay in getting a permit. The Lightfoot administra­tion instead “told HUD, in writing, that HUD had no right or jurisdicti­on to interfere with the City’s permitting process,” the court filing said.

“The City did not attempt to call off its Agreement with RMG. It did not tell RMG to continue operating on the North Side because the City could not abide by the Agreement. Instead, the City insisted that RMG follow through on its promise to cease operations [and] said the permit was imminent,” the filing said.

The company spent $80 million to build a new facility and, unless it can begin operation, is financiall­y vulnerable, the filing said.

Lightfoot halted the permit review process in May at the urging of the U.S. Environmen­tal Protection Agency’s top official, who said he was concerned about the rights of residents who live in an already heavily polluted area.

 ?? PROVIDED ?? Reserve Management Group built this $80 million metal-shredding facility on the Southeast Side. It claims in a court filing that the constructi­on continued as the city encouraged the company it would get an operating permit.
PROVIDED Reserve Management Group built this $80 million metal-shredding facility on the Southeast Side. It claims in a court filing that the constructi­on continued as the city encouraged the company it would get an operating permit.