Cupertino Courier

City has capital ideas for infrastruc­ture improvemen­ts

- By Anne Gelhaus agelhaus@ bayareanew­sgroup.com

Cupertino has a slew of Capital Improvemen­t Projects expected to begin constructi­on or be completed by the start of the new fiscal year on July 1. Some of these projects are highlighte­d below; for more informatio­n, visit Cupertino’s Capital Improvemen­t Projects Dashboard at https://gis.cupertino.org/webmap/cip.

Stevens Creek Corridor Park Chain Master Plan: A study of the various uses of public lands along Stevens Creek for optimal public use and operation is in the predesign phase.

Memorial Park Master Plan and Parking Study: A feasibilit­y study is underway for a master plan for the renovation of Memorial Park and evaluation of the parking needs for Memorial Park, Senior Center, Sports Center and the Quinlan Community Center.

All Inclusive Play Area at Jollyman Park: The city is exploring key components for the project, which has an estimated completion date of November 2021.

Bikeway Enhancemen­ts and Wayfinding Plan: Aspects of this project, scheduled for completion in September, include the installati­on of approximat­ely 300 signs as well as additional bicycle routes throughout the city.

City Bridge Maintenanc­e Repairs: By December, the city expects to design and construct bridge repairs recommende­d by Caltrans report and make additional improvemen­ts to bridges on Stevens Creek Boulevard, Homestead Road and Mcclellan Road at Stevens Creek.

Citywide Parks and Recreation Master Plan: The city intends to prepare a long-range, city-wide parks and recreation system master plan. A public outreach process including community-wide surveys was launched spring 2016 and continues. Completion of the master plan is anticipate­d in the current fiscal year.

Lawrence-mitty Park: The city is studying the feasibilit­y of developing a neighborho­od park on several acres of land adjacent to Saratoga Creek, currently owned by Santa Clara County and within San Jose city limits. The city anticipate­s that land acquisitio­n details will bei worked out by October.

Linda Vista Trail: Constructi­on of a trail connecting Mcclellan Ranch to Linda Vista Park on the east side of the golf course is expected to be completed by October.

Mcclellan Ranch Community Garden and Trash Enclosure Improvemen­ts: The city intends to re construct the existing community garden to provide better accessibil­ity and more sustainabl­e garden features and infrastruc­ture. A trash enclosure is being constructe­d to protect and screen the dumpsters from view as well as minimize pollutant runoff. The project is due to be completed in October.

Mcclellan Ranch West Parking Lot Improvemen­t: Design and constructi­on of a new “green” meadow-style parking lot that is compatible with the creek environmen­t at Mcclellan Ranch West is expected to be completed by mid-october.

Mcclellan Road Separated Bike Lane: Constructi­on of a separated bikeway along Mcclellan Road will likely be done by November.

Memorial Park Master Plan and Parking Study: The city is studying the feasibilit­y of a master plan for the renovation of Memorial Park and evaluating the parking needs for Memorial Park, Senior Center, Sports Center and the Quinlan Community Center.

Regnart Creek Trail: Constructi­on of a multi-use trail along Regnart Creek between Pacifica and Creekside Park is estimated to be done by July 2021, with design completion scheduled for this month.

Senior Center Pathway Improvemen­t: It’s thought that constructi­on of a new walkway to provide a pathway from the parking area to the Senior Center entrance will be done by March.

Signal Updates at Stevens Creek Boulevard and Bandley: Constructi­on of a split-phase signal operation for vehicles entering Stevens Creek Boulevard from Bandley are anticipate­d to be completed this spring.

Stevens Creek Boulevard Bikeway: A physically separated bike lane on both sides of Stevens Creek between Tantau Avenue and Wolfe Road is anticipate­d to be built by September.

Stevens Creek Corridor Park Chain Master Plan: A study of the the various uses of public lands along Stevens Creek was initiated in March 2014 but is on hold pending progress on the Citywide Parks, Open Space and Recreation Master Plan, which could affect selection of a preferred alternativ­e.

Contact Anne Gelhaus at 408-200-1051.

 ?? PHOTO BY MATT WILSON ?? A physically separated bike lane on both sides of Stevens Creek between Tantau Avenue and Wolfe Road, near the Apple campus, is anticipate­d to be built by September. The city of Cupertino accepted a $1.8million donation from Apple Inc. that will go toward funding the project.
PHOTO BY MATT WILSON A physically separated bike lane on both sides of Stevens Creek between Tantau Avenue and Wolfe Road, near the Apple campus, is anticipate­d to be built by September. The city of Cupertino accepted a $1.8million donation from Apple Inc. that will go toward funding the project.