Daily Freeman (Kingston, NY)

More woes for water customers?

Delayed work at roundabout site could add to dam-related rate hike

- By Paul Kirby pkirby@freemanonl­ine.com

The cost of installing new undergroun­d water pipes where a traffic roundabout is to be created at the intersecti­on of Albany Avenue, Broadway and Col. Chandler Drive could rise now that the state is seeking new bids for the entire project, the city water superinten­dent says.

Any additional cost for the water infrastruc­ture would be passed to ratepayers, Judith Hansen said Monday, just days after she said the cost of repairing the dam at the city’s reservoir could drive up water usage rates by 20 percent.

“The amount that we must provide to the state [for the work at the roundabout site] could increase if the amount of the water main replacemen­t increases as a result of the rebidding,” Hansen wrote in an email. “The board (city Board of Water Commission­ers) has agreed to replace our infrastruc­ture beneath the proposed roundabout since they believe that the actual constructi­on of the roadway will compromise the integrity of our existing infrastruc­ture and felt that they had little choice but replace these mains.”

The state is paying for the road project, but it is not covering the cost of any city infrastruc­ture that needs to be replaced.

Hansen said the Kingston Water Department has bonded $522,676 for pipe work at the roundabout site and gave that money to the state in the summer of 2018.

“We subsequent­ly were informed that the state decided to rebid the project, which will delay the project by about one year,” Hansen said. “The state has not refunded any of our funds, and we are currently making interest and principal payments of about $39,000 per year on a bond for a project that will not be completed until 2021.”

The state Department of Transporta­tion said last week that the need to solicit new bids for the project has pushed the anticipate­d completion date back to the fall of 2021.

Also last week, Hansen said the expected cost of repairing the dam at the city’s Cooper Lake reservoir, which is in the town of Woodstock, had soared by 140 percent — to $12 million from the original estimate of $5 million — and that if the Water Department is unable to secure grants to pay for part of the project, ratepayers’ water bills could jump by as much as 20 percent.

Regarding the roundabout delay, state transporta­tion spokeswoma­n Heather Pillsworth said bids submitted for the project were rejected.

“The DOT rejected all bids in order to re-examine the project and associated costs,” she said last week.

The roundabout initially was forecast to cost $7 million, but that estimate was raised to $13.1 million this past March, after the constructi­on bids were submitted.

Whether the estimate will rise or fall after new bids are submitted remains to be seen.

Kingston Alderman Douglas Koop, in whose ward the roundabout is to be built, said the delay provides “an opportunit­y to relook at the ... project.”

“Letting the project, with substantia­l cost escalation­s, proceed because someone else, i.e. the state, is paying for most of it is not necessaril­y good policy,” Koop, DWard 2, wrote in an email Monday.

Koop said he also has been made “aware of roundabout-related bicycle crash statistics that are very alarming and should not be ignored.”

Besides changing the flow of vehicular traffic, the roundabout is to include 10-foot-wide, mixed-use paths for pedestrian­s and bicyclists, as well as raised crosswalks.

Kingston Mayor Steve Noble on Monday said replacing city’s undergroun­d infrastruc­ture at the planned roundabout site is necessary, regardless of the state project.

“As I stated before, repairing critical water and sewer line infrastruc­ture is vital to maintain our clean and safe drinking water system and wastewater system,” Noble wrote in an email. “Regardless of whether the roundabout is built now or later, the pipes are over 100 years old and need to be replaced. DOT went back to bid because of unexpected­ly high estimates, and is hoping to see lower cost estimates with the next round of bids later this year.”

Noble and the Kingston Common Council have authorized spending about $1.1 million for new sewer pipes at the roundabout site.

 ?? FILE PHOTO BY TONY ADAMIS ?? The roundabout is to be constructe­d at the intersecti­on of Albany Avenue, Broadway and Col. Chandler Drive in Kingston, N.Y. This photo looks north on Albany Avenue, with Broadway coming in from the right and Col. Chandler Dive (I-587) at the left.
FILE PHOTO BY TONY ADAMIS The roundabout is to be constructe­d at the intersecti­on of Albany Avenue, Broadway and Col. Chandler Drive in Kingston, N.Y. This photo looks north on Albany Avenue, with Broadway coming in from the right and Col. Chandler Dive (I-587) at the left.

Newspapers in English

Newspapers from United States