Daily Local News (West Chester, PA)

WEST GOSHEN Hundreds oppose pipeline project

Constructi­on already well underway on Mariner East 2 Pipeline in county

- By Bill Rettew brettew@dailylocal.com

Although constructi­on of Sunoco Logistics’ Mariner East 2 Pipeline is underway, hundreds of residents continue to oppose the project.

Two West Goshen residents and six Middletown Township, Delaware County, residents have field separate lawsuits in Commonweal­th Court to uphold zoning regulation­s in a bid to halt constructi­on of ongoing work and additional pipeline constructi­on in the future.

Constructi­on of the 350-mile long Sunoco Mariner East 2 pipeline is underway in Chester and Delaware counties. When completed, the company says it will transport more than 350,000 barrels of ethane, butane and propane from the state’s Marcellus Shale region to the former refinery in Marcus Hook, mostly for shipment overseas.

Mark Freed, an attorney with Curtin Heefner LLP, is representi­ng West Goshen residents. Freed pointed to a three-part 2014 township ordinance.

He claims that the townshipcr­eated ordinance makes it il-

legal for pipelines to pass through residentia­l neighborho­ods, which Sunoco plans to do.

He also said that even where pipelines are allowed, conditiona­l use approval from the board of supervisor­s is required.

Sunoco plans call for constructi­on in “blast zones,” Freed said, claiming that structures housing people are located closer to proposed pipelines than allowed by township law.

Eric Friedman is the spokespers­on for the Middletown Coalition for Community Safety.

“All the residents are asking for is that Middletown’s ordinances be enforced,” Friedman said.

Friedman said that existing ordinances call for a 75foot setback from occupied structures, while Sunoco plans call for the pipeline to run much closer to households, churches and schools.

Plans call for the pipeline to carry ethane, as well as butane and propane. All three are liquids that turn to a colorless, odorless gas that stays low to the ground when exposed to the air.

Residents are told to run upwind for a half mile in case of a leak and that a cell phone, car engine or doorbell could set off an explosion.

Tom Casey is a plaintiff in the West Goshen lawsuit. He’s fought the pipeline

project since he first heard about it.

“Sunoco believes they exempt from local zoning – they don’t have to follow it,” Casey said. “(By suing) I’m doing what the township should be doing for its residents.”

Sunoco Logistics has acknowledg­ed residents’ concerns, but insists that constructi­on meets all zoning regulation­s and that safety standards in both constructi­on and ongoing maintenanc­e of the pipeline are of the highest industry standard.

Casey, a losing candidate for supervisor in the May primary, cited 2014 township ordinances.

“We have a zoning ordinance that was designed to protect this township,” he said. “It’s a law. They must follow it like you or I must follow the laws. Sunoco must play by the rules, they’re not exempt.”

Elaine McLaughlin owns a home in East Goshen and runs a business in West Goshen. Both are impacted by the planned pipeline.

She said that a Sunoco representa­tive told her that the pipeline near her home will snake beneath the roadway. After viewing ongoing constructi­on, she worries about preserving 26 trees in her backyard.

“I’m frustrated, angry and disappoint­ed,” she said about East Goshen Township’s role. “It looks like a war zone.”

McLaughlin, and many others, including Casey, are not just fighting current

constructi­on but the possibilit­y that other pipelines will run through Chester County.

Chester County hosts the third most number of pipelines on a pathway to the refinery in Marcus Hook.

Casey LaLonde, West Goshen Township manager said that the township continues to pursue the matter with the state Public Utilities Commission, with a special township counselor attending every recent board of supervisor­s meeting.

Several residents have met with West Chester Area School District Superinten­dent Dr. James Scanlon. Three WCASD schools are located within the blast zone, the area that could be affected in the event of a leak and subsequent explosion.

Scanlon said the school district is scheduling a regular annual meeting with police to discuss evacuation strategies.

“We’re putting a plan in place,” Scanlon said. “We’re taking our lead from Emergency Management Services.”

Scanlon said that in case of a leak, students would either stay put, evacuate to another area or a combinatio­n of both.

“We have been reviewing our safety protocol in the event of a gas leak during the school day,” he said. “The scope of our planning extends well beyond what the school district can do and will need to involve emergency responders in the process.”

 ?? BILL RETTEW JR. – DIGITAL FIRST MEDIA ?? Constructi­on of the Sunoco Mariner East 2 Pipeline is well underway on North Chester Road, a quarter mile north of Manley Road.
BILL RETTEW JR. – DIGITAL FIRST MEDIA Constructi­on of the Sunoco Mariner East 2 Pipeline is well underway on North Chester Road, a quarter mile north of Manley Road.