Daily Times (Primos, PA)

Nether Providence panel: Demolish Summit School

- By Neil Sheehan Times Correspond­ent

NETHERPROV­IDENCE >> Nearly three years after the township acquired the former Summit School property, an 11-member study committee has determined the building there is in such poor shape it should be demolished.

The township commission­ers agreed with that conclusion and authorized the solicitati­on of bids for razing of the structure at the Plush Mill Road site.

“The board is seeking cost estimates and funding when an opportunit­y arises,” municipal Manager Gary Cummings said. “We may be seeking Community Developmen­t Block Grant funding in the

2019 funding cycle.”

As to what might happen next with the property, the study committee has recommende­d the developmen­t of new athletic fields and a playground; the constructi­on of a community center; and possibly a passive park, bird sanctuary and/or walking trail.

Monies from such sources as grants would have to be secured before those ideas could be pursued.

Among those on the committee were two commission­ers, Matthew Garson and Kaitlin McKenzie-Fiumara; planning commission member Bob Linn; a parks commission member, Steve Henry; and seven residents.

The panel held twicemonth­ly public meetings from March through October of this year and explored all possible options for the property, which the township purchased in 2016 from the Wallingfor­d-Swarthmore School District for $925,000.

Options considered included complete renovation of the existing 28,500-squarefoot building, sale of the property and continued use of the structure as is. Several performing arts and community groups and organizati­ons currently use the facility.

Factors that weighed against the last possibilit­y were the size and shape of the complex – a main building with three pod sections; the condition of the roof; the presence of mold; energy-inefficien­t windows; and the cost of addressing HVAC and electrical systems in poor condition.

The estimated price tag for repairs and renovation­s was pegged at about $3 million.

“After careful considerat­ion, it is the opinion of the committee that this existing building does not lend itself well as a candidate for adaptive reuse,” the panel told the commission­ers during a presentati­on in October.

With respect to a community center at the site, the committee stated it was looking at a new 11,500-square-foot building, with the possibilit­y of a 6,600-square-foot expansion at some point.

Linn, who is an architect, said the center would cost about $2.5 million. Other projected costs were $150,000 for a baseball field, $50,000 to

$60,000 for a basketball court,

$35,000 to $50,000 for a basketball court and $125,000 for a parking lot.

The committee listed the following possibilit­ies for grants to help pay for the expenditur­es:

• State Department of Conservati­on and Natural Resource’s C2P2 Program – There is no limit on the grant funding, but requires a 50-percent\ match

• Greenways, Trails and Recreation Program — Up to

$250,000, 15-percent match required. Other state agency funds may be used as the cash match, including funds from C2P2.

• Redevelopm­ent Assistance Capital Program (RACP): — A project must have a total cost of at least $1 million and requires a 50-percent match. However, funds from other state sources, including legislativ­e sources, may not be used as match.

• State Department of Community and Economic Developmen­t’s Community Developmen­t Block Grant (CDBG): Up to $250,000.

• County Conservati­on and Recreation Program: The township received $100,000 in funding from this program to assist with the purchase of the site.

• State Community Facilities Direct Loan & Grant Program — Up to 35-percent of cost; it would require a 65-percent

match.

• Community Facilities Technical Assistance and Training Grant

• DCED Municipal Assistance Program (MAP)

When township officials in late 2015 disclosed that they had struck a deal with the school district to purchase the property, then-Board of Commission­ers President Nate Much said, “This is a once-ina-lifetime opportunit­y. We simply can’t pass it up.”

Financing for the transactio­n broke down as follows:

$600,000 from money left to the township by a couple;

$100,000 from the state grant; and the remaining $325,000 from a loan from the township’s sewer fund.

 ??  ?? A township panel has decided it would cost too much to renovate the former Summit School in Nether Providence and instead has recommende­d the building be demolished.
A township panel has decided it would cost too much to renovate the former Summit School in Nether Providence and instead has recommende­d the building be demolished.