Timeline of compliance efforts

-

The City of Rochester provided a timeline of events, beginning in 2009, of efforts to bring the reservoirs into compliance with the LT2 requiremen­ts. The timeline begins with the bilateral compliance agreement between the city and the state and county health department­s, which required additional sampling for cryptospor­idium.

● The original compliance date was October 2014 for Highland Park and November 2013 for Cobb’s Hill; in 2012 the compliance agreement was extended to 2023 and 2024 for Highland Park and Cobb’s Hill, respective­ly.

● In 2012, Rush Reservoir is covered with a floating synthetic rubber cover, meeting the compliance deadline for the reservoir without public access.

● In 2018, Bergmann Associates, now rebranded as Colliers Engineerin­g and Design, is contracted to re-evaluate options and conceptual designs to bring Highland Park Reservoir into compliance with LT2. The study is halted in 2020 for a corrosion control study to align with new lead regulation­s.

● In 2021, the bilateral compliance agreement is revised, giving the city time to complete corrosion study and determine if orthophosp­hate is required to control lead. The compliance dates are pushed out to November 2029 for Highland Park Reservoir and November 2035 for Cobb’s Hill Reservoir.

● Also in 2021, the city entered an agreement with Ramboll/CDM Smith for the corrosion control treatment study and remains in the testing phase, expected to take 18 months to complete.

● This year, the city entered an agreement with Colliers Engineerin­g and Design to re-evaluate options and bring the Highland Park Reservoir into compliance with LT2 and the Lead and Copper Rule revisions.