Greenwich Time

GHS field cleanup is ‘moving forward’ on schedule

- By Justin Papp

PCBs and other harmful materials were discovered under the high school’s western parking lot after work began on the Music Instructio­nal Space and Auditorium in 2011.

GREENWICH — Remediatio­n work on one of Greenwich High School’s athletic fields is progressin­g on schedule, according to town officials.

Phase II of the larger fields remediatio­n project at Greenwich High began this summer and will continue into the fall in an effort to remove PCBs and other harmful materials that were first discovered at the site in 2011. The district is carrying out the project in partnershi­p with the Connecticu­t Department of Environmen­t and Energy and the federal Environmen­tal Protection Agency.

“We are continuing to make progress on the soil remediatio­n project at the high school in partnershi­p with the Town of Greenwich Department of Public Works,” Superinten­dent of Schools Toni Jones said. “The work happening this summer is currently on track as outlined in our community updates.”

A first phase of remediatio­n was mostly completed in summer 2020 and involved the replacemen­t of turf coverings on athletic fields 6 and 7 and the insertion of crushed rock on top of the soil beneath.

Phase II is larger in scope and could take three years to complete, according to the school district. It will focus primarily on fields 2, 3, 4 and 5, with the cleanup work conducted during the summer months and the restoratio­n and constructi­on of the fields during the fall.

The cleanup work cur

rently underway has made fields 2, 3, 4, 5, 6 and 7 unavailabl­e for use, according to the district, as crews work in the vicinity of field 4.

Plans for fall 2021 include the installati­on of a new impermeabl­e cap beneath field 4 and the constructi­on of new artificial turf atop the cap. Field 2, 5, 6 and 7 will be open to the public. A portion of field 3 will also be open to the public, though the length of the field will be limited by the work on field 4.

“Work is occurring Monday through Saturday, all to keep the project moving forward as quickly as possible,” First Selectman Fred Camillo wrote last week in his regular community email update.

As Phase II progresses, the school district continues to work with DEEP and the EPA to finalize plans and obtain approval for the remainder of the remediatio­n project on the site.

The remediatio­n project carries an estimated $25 million price tag.

PCBs and other harmful materials were discovered under the high school’s western parking lot after work began on the Music Instructio­nal Space and Auditorium in 2011. The contaminat­ed soil had been moved to the site in the 1960s and 1970s to shore up wetlands so the school building could be constructe­d.

Phase II of the project includes removing hazardous materials, as deep as 10 feet below the ground in some areas, from Fields 3, 4 and 5, on the western side of campus. The aim of the project is to prevent direct contact with the harmful materials, as well as the contaminat­ion of groundwate­r via storm-water infiltrati­on.

 ?? Town of Greenwich / Contribute­d photo ?? Crews work to remove contaminat­ed soil under the athletic fields at Greenwich High School on Monday. The remediatio­n project is progressin­g on schedule and will continue through the new school year.
Town of Greenwich / Contribute­d photo Crews work to remove contaminat­ed soil under the athletic fields at Greenwich High School on Monday. The remediatio­n project is progressin­g on schedule and will continue through the new school year.
 ?? Contribute­d image ?? Plans for the Phase II soil remediatio­n of Greenwich High School fields.
Contribute­d image Plans for the Phase II soil remediatio­n of Greenwich High School fields.

Newspapers in English

Newspapers from United States