Houston Chronicle

Flooding effects push back dam upgrade

U.S. Army Corps of Engineers projects that work could be finished by fall 2019

- By Sebastian Herrera

When record flooding submerged parts of Houston in April, the Addicks and Barker reservoirs near the Energy Corridor were among the most impacted structures.

Weeks later, that impact can still be felt as long-anticipate­d renovation­s to the reservoirs’ dams have been pushed back by months.

A $72 million overhaul to the dams, which are more than 70 years old, had begun in April before the flooding. Now, the contractor in charge of constructi­on, Granite Constructi­on Co., won’t be able to begin assessing the restoratio­n process again until sometime in July after both the Addicks and Barker reservoirs are finished draining.

The contractor “was doing pretty good before the rain hit,” said John Long, resident engineer at the U.S. Army Corps of Engineers Galveston District, which oversees the reservoirs. “We won’t know for sure how long the delay is until we do an analysis.”

In 2009, the district self-labeled the dams as “extremely high risk” for flood control based on technical problems that might cause dire consequenc­es if the dams were to fail during a major storm.

West Houston saw between 12-17 inches of rain during the Tax Day floods, and water from the downpour quickly rose in the reservoirs, eventually spilling into nearby streets and residences.

Despite experienci­ng record-setting levels of water, both reservoirs held their ground during the flooding, according to Rick Villagomez, the renovation­s project manager.

“The dams did not experience any damages when rains hit,” Villagomez said. “We continue now to monitor the dams, and to our knowledge, there is no issues with the structures themselves.”

Even now, the normally dry Addicks reservoir remains approximat­ely 20 percent full while the Barker reservoir is at about an equal percentage of capacity, according to Ralph Steiner, the area engineer at the district.

The dams protect an estimated 1.2 million Houstonian­s by taking in excess water from Buffalo Bayou.

This isn’t the first time the constructi­on project has been delayed. Constructi­on should have begun in September 2015 after the district approved a constructi­on contract with Granite Constructi­on. Delays occurred then as the district awaited notice to proceed from the federal government, which is funding the developmen­ts.

The delays will cause constructi­on costs to rise, Long said.

“Yes, (the delays) are frustratin­g, but we have it within our contract to deal with this situation,” Long said. “The contractor is taking great steps to mitigate costs; so we are not expecting large cost increases.”

The renovation­s include developing new intake towers, cutoff walls and downstream filters.

Since 2009, the district has implemente­d interim measures while it waited to begin renovation­s. The measures included constructi­ng a granular filter around the ends of the outlet structure, which gives the dams added strength, and installing additional lighting for inspection and monitoring.

As it awaits to see when the major renovation­s can begin again, Granite Constructi­on has been handling light maintenanc­e throughout the dams, Villagomez said.

The dams were constructe­d after catastroph­ic floods in both 1929 and 1935. The more recent large flooding events in 2009, 2015 and this year have tested the aged dams’ limits.

The renovation­s were scheduled to be completed around May 2019 but will now be pushed back to a September 2019 finish, Steiner said.

And that’s if the weather plays nice in the unpredicta­ble swamp that is Houston.

 ?? Jimmy Loyd / For the Chronicle ?? John Long looks over the Addicks Reservoir near Texas 6 and Interstate 10.
Jimmy Loyd / For the Chronicle John Long looks over the Addicks Reservoir near Texas 6 and Interstate 10.

Newspapers in English

Newspapers from United States