Cost dispute still plagues light rail cars

- By Dug Begley

Houston’s light rail system is fully open, but closing out a complicate­d railcar purchase that nearly derailed the new lines remains a challenge for transit officials.

Metropolit­an Transit Authority officials continue withholdin­g $12.9 million from CAF U.S.A. — the builder of the vehicles — as they debate the amount of liquidated damages owed because of delays and delivery of railcars that were overweight, leaky and halted by faulty axles, among other problems.

When those discussion­s could conclude and what sort of damages Metro could receive is uncertain, transit agency CEO Tom Lambert said.

“We are not there yet,” he said. “We are going to continue to work with CAF, address the issues and go from there.”

In the meantime, the Metro board on Thursday extended a contract with Parsons Transporta­tion Group, an engineerin­g and design firm, for oversight of the CAF purchase. The extension carries the contract beyond its previous expiration in May to April 2018 and adds nearly $700,000 to the contract, which has already paid Parsons $29.6 million.

All 39 of the new light rail cars purchased are available for service, and car-

ried a higher-than-normal number of passengers because of the Houston Livestock Show and Rodeo.

All of the cars, however, also have a handful of fleet defects that CAF will have to correct, said Scott Grogan, Metro’s senior director of rail operations.

Series of problems

Defects are not unusual in railcar production, and CAF has had some notable failures in other cities lately.

In December, CAF-built vehicles were shelved in Cincinnati for various mechanical issues. Washington D.C.’s transit system — far larger than Houston’s — has had widespread maintenanc­e issues with older and newer trains.

Though an axle issue parked some of Houston’s trains more than a year ago, the manufactur­ing defects do not compromise safety. The axle issue remains the most pressing and complicate­d defect to remedy, officials said.

CAF is also working on 18 modificati­ons to the trains, related to seven identified defects. A problem is considered a defect when 10 percent of the trains have the same problem, officials said. “All of these that have been identified have an engineerin­g resolution,” Grogan said.

He said CAF maintenanc­e can be performed at Metro’s maintenanc­e garage, without disrupting rail service. Trains will be brought in one at a time as parts arrive.

“We will go through that process 39 times,” he said.

Metro’s preliminar­y schedule calls for all but two of the modificati­ons to be made by the end of the year.

Replacemen­t of a resilient wheel that distribute­s power to the train’s axles is expected to take until February, while the broader axle installati­ons will take until March 2018. The first batch of new axles is not expected until July.

The axle problems are just the most recent in years of struggle with the railcars. The bleak history has fueled critics and frustrated even rail supporters.

“I love Metro,” said Chuck Baiul, 41, who lives in EaDo near the Green Line and often rides it. “But boy, does it seem like they step in it. Things take longer and cost more than they should.”

In 2010, Metro risked losing its $900 million in federal funding to expand the Red Line and build the Purple Line when the Federal Transit Administra­tion determined CAF wasn’t complying with Buy America requiremen­ts by doing too much of the work abroad. CAF U.S.A. is a subsidiary of the Spanish train-builder Construcci­ones y Auxiliar de Ferrocarri­les.

Work was moved to a CAF plant in Elmira, N.Y., which was slow in filling Metro’s order.

By 2013, as the first car arrived, the builder was months behind schedule and quality concerns arose. Spanish officials with the company personally visited Houston, reassuring Metro officials and pledging expansion of the Elmira plant to accelerate delivery.

Things proceeded until late 2015, six months after most of the expanded light network opened, when the axle issues parked 14 of the cars so officials could assess the problem.

Buoyed by Super Bowl

The cars are only part of the stumbles related to the rail lines that Metro has raced to correct. Axle counters along the line led to delays in service for months, dropping on-time performanc­e.

Timing has improved significan­tly since a blitz of repairs prior to the Super Bowl held last month in Houston. In January, the Red Line posted its highest on-time percentage, 92.6 percent, since November 2015. For many of the months between, fewer than 80 percent of the trains arrived on time.

Officials said that despite the lingering issues and unresolved matters, the system is carrying people and growing. Buoyed by heavy use for the Super Bowl week, light rail weekday ridership was 2 percent higher in February, compared to the same month last year.

On Saturdays and Sundays, use increased 12 percent and 13 percent, respective­ly.

“This isn’t limiting our ability to provide service,” board member Christof Spieler said of the railcar repairs.