Houston Chronicle

County ends Crosby-Lynchburg contract

- By David Taylor

The Harris County Engineerin­g Department on Jan. 23 announced a contract terminatio­n with the contractor working on the Crosby-Lynchburg Road Segment 4 expansion between Lochness Drive and Thorn Street in the Crosby-Highlands area.

The project is the conversion of a two-lane road to a five-lane boulevard.

“Although work has stopped in the interim along this segment, the contract terminatio­n is pending review and approval at Harris County Commission­er’s Court,” the announceme­nt from Harris County Precinct 3 Commission­er Tom Ramsey’s Office said.

Only half of the roadway segment is completed.

With the original $6 million contract going to Aranda Brothers Constructi­on Company, Inc., constructi­on began in August 2021 and was expected to be finished in August 2022, almost five months ago.

“The execution of the contract to this point has resulted in ‘terminatio­n for convenienc­e,’” said Jon Steiber, senior project manager with Pct. 3.

“Terminatio­n for convenienc­e” is a clause in a contract that allows the contract to be terminated without a potentiall­y costly default dispute in court, according to Matt Viator at levelset.com. Terminatin­g a contract based on convenienc­e often provides a much cleaner break, he said.

“Terminatio­n for convenienc­e is sort of like at-will employment or a prenup. When a contract is terminated for convenienc­e, the contract is being terminated simply because one party decides to terminate the agreement. It’s not necessaril­y due to poor performanc­e, and it’s not because one party breached the agreement. However, terminatio­n of convenienc­e will only be an option where a contract features a terminatio­n for convenienc­e clause,” Viator explains in an article on the Levelset blog.

Otherwise, the terminatio­n of a regular contract can be like a divorce, he says: messy and costly.

According to Steiber, stoppage began this month and was in the best interest of county taxpayers.

Although completion of the road segment will be delayed, Steiber said the engineerin­g department will ensure that traffic control “is maintained to provide safe travel lanes as the constructi­on contract is rebid,” according to the announceme­nt.

The timeline and cost to finish the contract is currently under evaluation by the design engineer.

The engineerin­g department is in the process of preparing to rebid the remainder of the constructi­on contract with constructi­on expected to resume during the third quarter of 2023.

Steiber said the northbound concrete lanes are completed.

“Traffic has shifted from the old asphalt southbound lanes to the new concrete lanes in January 2023 and safety and trafficabi­lity are significan­tly improved,” he said.

Steiber said the work completed to this point complies with county requiremen­ts.

For more informatio­n, contact Jon Steiber with Harris County Precinct 3 Commission­er Tom Ramsey’s Office at 713-274-3112 or Jonathan.Steiber@pct3.hctx.net.

Newspapers in English

Newspapers from United States