Delays plague San Bernardino’s Mt. Vernon Avenue Bridge project

- Amy Bentley Columnist

QMartha Uribe of Fontana recently asked when the Mt. Vernon Avenue Bridge in San Bernardino would be rebuilt and completed. The bridge was closed a couple of years ago, she said, adding, “No efforts to rebuild it have been made.”

ARebuildin­g efforts are indeed underway but the project has been delayed by numerous factors. Here is an update on the Mt. Vernon Avenue Bridge Project from Tim Watkins, the San Bernardino County Transporta­tion Authority’s chief of Legislativ­e and Public Affairs.

First, a little background: The old Mt. Vernon Avenue Bridge opened in 1934. For safety reasons, San Bernardino, Caltrans and the San Bernardino County Transporta­tion Authority partnered to tear it down and rebuild a new and improved bridge. They closed the old bridge in December 2020 and demolition was complete in April 2021. Reconstruc­tion was supposed to start this year with an opening date in 2024. The new bridge will have wider lanes, a center median, wider sidewalks and new bike lanes, and serve pedestrian­s, bicyclists, cars and commercial vehicles. Here is the project website: https://www.gosbcta. com/project/mt-vernonviad­uct/

Watkins noted that this project spans one of the largest rail yards in the region. Because the old bridge was rated as severely deficient, for safety reasons it had to be torn down as soon as possible, while the design/build team finalized reconstruc­tion. In addition, the operators of the railyard, BNSF Railway had its own work to do to realign some rail lines to maintain operations during bridge reconstruc­tion. “As a result, the project was staged where the reconstruc­tion would be suspended during the BNSF operation,” Watkins said.

“The original schedule made some assumption­s on indetermin­ate items like utilities, property acquisitio­n and other right of way issues,” he said. “Unfortunat­ely, those areas took a little longer than anticipate­d and BNSF was delayed in commencing their work until they were resolved. However, BNSF assures us that their work will be complete in 2023 and we can begin the primary reconstruc­tion immediatel­y thereafter.”

The city, transporta­tion agencies and rail operators are coordinati­ng to do what work they can concurrent­ly to make up some lost time, he said. As Watkins pointed out, “Project delivery is not an exact science as there are multiple variables that factor into the progress made on projects.”

“While the reconstruc­tion did not commence according to our original estimates, we are continuall­y looking for opportunit­ies to advance the project to completion,” he said. “We remain optimistic that we will complete the project by the end of 2024, however, production rates and other timerelate­d elements of the constructi­on process may move us toward the early part of 2025.”

Do you commute to work in the Inland Empire? Spend a lot of time in your vehicle? Have questions about driving, freeways, toll roads or parking? If so, write or call On the Road and we’ll try to answer your questions. Please include your question or issue, name, city of residence, phone number and email address. Write ontheroad@scng.com or call 951-368-9670.

 ?? ??