Las Vegas Review-Journal (Sunday)

US aims to restore water, fish to diverted river

Cost too high, benefits too few, farmers say

- By SHARON BERNSTEIN

FRESNO, Calif. — California’s San Joaquin River flows out of the mountains above Yosemite, clear and bubbling until it abruptly stops just north of Fresno, its water diverted to irrigate farms.

Environmen­talists have cheered a plan to reconnect the river this fall. But it is over budget, overdue and vehemently opposed by local farmers and some Republican lawmakers. U.S. Sen. Ted Cruz of Texas, a 2016 Republican presidenti­al hopeful, once joked about eating its protected fish with crackers.

“For somebody who doesn’t really understand about the issue it seems very simple — just reconnect the river and water will flow,” said Cannon Michael, a sixth-generation farmer whose family settled in the San Joaquin Valley in the 1800s. “But the river was disconnect­ed for a reason.”

Initially diverted to provide water for agricultur­e and encourage family farms, the San Joaquin River has become the latest battlegrou­nd of California’s century-old water wars. Its dams, hydro-electric plants and diverted flow illustrate the benefits as well as the costs of 20th century efforts to tame the state’s natural resources.

Damming the river in 1942 was an engineerin­g feat that made the San Joaquin a keystone of a complex water system that allowed a semi-arid state to provide water for 40 million residents and grow more fruits and vegetables than any other U.S. state, on land watered almost entirely by irrigation.

But constructi­on of Friant Dam near Fresno also eliminated the Pacific Coast’s southernmo­st runs of Chinook salmon. The river is dry most years along two stretches for a total of 60 miles. It was recently named the second-most endangered U.S. river by the group American Rivers.

“Old-timers tell stories of the water being so thick with salmon that you could practicall­y walk across it,” said Doug Obegi, an attorney with the Natural Resources Defense Council.

In 1988, that environmen­tal group sued the federal government, saying diverting the river broke state law protecting fish. After 18 years of court battles, environmen­talists, the federal government and water users finally agreed to restore the river to again support salmon.

Since that 2006 settlement, efforts to restore the river have been slowed by engineerin­g challenges, tense negotiatio­ns with farmers and other delays. The U.S. Bureau of Reclamatio­n, which operates Friant Dam, is now set to release enough water to reconnect the river this fall, program manager Alicia Forsythe said.

But improvemen­ts targeted for completion by 2013, including levees to prevent flooding and screens to keep threatened fish out of irrigation canals, have yet to start.

Environmen­talists, government officials and farmers are still arguing over the path the river should take because agricultur­al land has encroached on its traditiona­l route.

And farmers who rely on water diverted at Friant Dam will get less under the plan. Their allocation­s will drop by about 18 percent as more water is allowed to flow downstream.

Near Mendota, where levee constructi­on is planned to start next year, a road runs across the dry riverbed. Abandoned furniture sits in the dirt, and a target with bullet holes hangs from a tree.

Costs have ballooned, rising from an estimated $250 million to $800 million in 2006 to $1.5 billion today, Bureau of Reclamatio­n spokesman Shane Hunt said.

The latest projected completion date is 2029.

“It’s a giant waste of time and money,” said Greg Pearl, who farms 800 acres near the river.

U.S. Rep. Devin Nunes, a Republican who represents part of the area, said the cost of restoring the river is too high and the benefits too few. He backs a plan to build a reservoir upstream of Friant Dam so farms and communitie­s can have access to more water from the San Joaquin, not less.

Republican­s in the U.S. Congress have attached proposals to do that to several bills, some getting as far as the Senate before stalling there. A compromise brokered two years ago by Democratic Sen. Dianne Feinstein also stalled.

Among conservati­onists, however, excitement about re-connecting the river is palpable.

Former Natural Resources Defense Council scientist Monty Schmitt predicted dramatic results even from this fall’s planned releases of modest amounts of water, designed not to flood riverbanks before levees are built.

“In the span of five minutes you can go from a dry channel to a river that is 30 feet wide,” he said.

 ?? GARY KAZANJIAN/REUTERS ?? Farmer Greg Pearl walks at the Arroyo Canal/Sack Dam area during a July 8 tour of the San Joaquin River restoratio­n project near Firebaugh, Calif. The project is “a giant waste of time and money,” Pearl says.
GARY KAZANJIAN/REUTERS Farmer Greg Pearl walks at the Arroyo Canal/Sack Dam area during a July 8 tour of the San Joaquin River restoratio­n project near Firebaugh, Calif. The project is “a giant waste of time and money,” Pearl says.
 ??  ?? The old water gates at a control structure is seen during a tour July 8 of the San Joaquin River restoratio­n project near Firebaugh, Calif. The project could fill the area with water.
The old water gates at a control structure is seen during a tour July 8 of the San Joaquin River restoratio­n project near Firebaugh, Calif. The project could fill the area with water.

Newspapers in English