Las Vegas Review-Journal

Project Neon work showing progress

- ROAD WARRIOR

LOOKING past the traffic jams and fields of orange cones, tangible results are finally springing up from Project Neon.

Thirteen of the 28 planned bridges along Interstate 15 and U.S. Highway 95 were completed last year, with the remainder scheduled for constructi­on through 2018.

And 14 of the 42 planned Active Traffic Management signs were installed around the Spaghetti Bowl interchang­e, with the first six digital displays expected to be switched on next month.

From all appearance­s, several people who live and work near Nevada’s busiest freeway interchang­e appear pleased with what they’re seeing so far.

“We live right in the epicenter, and I’m impressed with how it’s progressin­g very smoothly and very respectful­ly for the neighborho­od,” Keith Resnick of Las Vegas said. “It could have been a real mess, but they’ve done a great job coordinati­ng their work and getting it done well.”

About 60 people gathered on Wednesday at the Historic Fifth Street School in downtown Las Vegas to attend the Nevada Department of Transporta­tion’s final public meeting to discuss the ongoing work along I-15 and U.S. 95.

Dale Keller, NDOT’S senior manager for the project, seized the moment to explain what’s coming next for the state’s largest infrastruc­ture project.

The final round of major closures, known as the “Main Event,” will allow for the most significan­t amount of work for Project Neon, while also affecting the most drivers for nine months.

NDOT crews will close several traffic lanes and freeway ramps around March 6. Here’s a rundown:

Both directions of I-15 will be narrowed to three lanes between Sahara Avenue and Washington

WARRIOR

Avenue, then further reduced to two lanes each way in the area immediatel­y surroundin­g the Spaghetti Bowl interchang­e.

The ramp connecting southbound U.S. 95 to southbound I-15 will be reduced to one lane.

The ramp linking southbound U.S. 95 to northbound I-15 will remain closed.

I-15 offramps at Charleston Boulevard, Martin Luther King Boulevard and D Street will have “longterm” closures.

The centerpiec­e of Project Neon is an 81-foot-tall flyover ramp for high-occupancy vehicles, which is about 60 percent complete, Keller said.

By the time it opens in 2019, the new carpool ramp will have one lane for drivers headed from southbound U.S. 95 to southbound I-15 and another connecting northbound I-15 to northbound U.S. 95. The two-way concrete ramp will be accessible from the center lane of both freeways.

Keller said that commuters can expect further closures when Project Neon heads into the final stretch in 2019, when crews will reconfigur­e the area around Grand Central Parkway and Charleston Boulevard to create a new “Neon Gateway” with a walking path and public artwork.

A series of steel posts in varying heights and colors will give the impression of an undulating pattern with a 35-foot-tall sculpture known as “Hot Dip.” A second sculpture, known as “Found Font,” will appear to emerge from the ground, stretching about 60 feet long and rising about 25 feet high.

“I feel like some some of these illustrati­ons are misreprese­ntative of the area because I’m seeing pictures of people taking a stroll, and most people don’t do that because it’s not a safe area,” said Brittaney Pearson of Las Vegas, who works near the constructi­on zone.

“To me, this implies there’s going to be a shift, maybe some gentrifica­tion that will drive some people out,” Pearson said. “It looks nice, but I believe there’s a hidden agenda.”

NDOT spokesman Tony Illia said he wasn’t aware of any plans to redevelop the neighborho­ods surroundin­g the Spaghetti Bowl interchang­e, but he said new transporta­tion infrastruc­ture usually leads to new developmen­t and investment­s.

Implied crosswalk

Patrick from Las Vegas said he lives in a senior citizen community near Sandhill Road and Briarwood Avenue in the east valley, which has an unmarked implied crosswalk.

With many of his neighbors using canes, walkers and wheelchair­s to get around, Patrick wanted to know whether Clark County officials could reduce the speed limit in this area.

County spokesman Dan Kulin said the intersecti­on was studied in 2015, and traffic engineers found that “the number of pedestrian­s in this area was not enough to warrant changes”

 ??  ??

Newspapers in English