How California’s bullet train went off the rails

- By Ralph Vartabedia­n

LOS ANGELES — Building the nation’s first bullet train, which would connect Los Angeles and San Francisco, was always going to be a formidable technical challenge, pushing through the steep mountains and treacherou­s seismic faults of Southern California with a series of long tunnels and towering viaducts.

But the design for the nation’s most ambitious infrastruc­ture project was never based on the easiest or most direct route. Instead, the train’s path out of Los Angeles was diverted across a second mountain range to the rapidly growing suburbs of the Mojave Desert — a route whose most salient advantage appeared to be that it ran through the district of a powerful Los Angeles county supervisor.

The dogleg through the desert was only one of several times over the years when the project fell victim to political forces that have added billions of dollars in costs and called into question whether the project can ever be finished.

Now, the tortured effort to build the country’s first highspeed rail system is a case study in how ambitious public works projects can become perilously encumbered by political compromise, unrealisti­c cost estimates, flawed engineerin­g and a determinat­ion to persist on projects that have become too big to fail.

A New York Times review of hundreds of pages of documents, engineerin­g reports, meeting transcript­s and interviews with dozens of key political leaders shows that the detour through the Mojave Desert was part of a string of decisions that, in hindsight, have seriously impeded the state’s ability to deliver on its promise to create a new way of transporti­ng people in an era of climate change.

Political compromise­s, the records show, produced difficult and costly routes through the state’s farm belt. They routed the train across a geological­ly complex mountain pass in the San Francisco Bay Area. And they dictated that constructi­on would begin in the center of the state, in the agricultur­al heartland, not at either of the urban ends where tens of millions of potential riders live.

The pros and cons of these routing choices have been debated for years. Only now, though, is it becoming apparent how costly the political choices have been. Collective­ly, they turned a project that might have been built more quickly and cheaply into

a behemoth so expensive that, without a major new source of funding, there is little chance it can ever reach its original goal of connecting California’s two biggest metropolit­an areas in 2 hours, 40 minutes.

When California voters first approved a bond issue for the project in 2008, the rail line was to be completed by 2020, and its cost seemed astronomic­al at the time — $33 billion — but it was still considered worthwhile as an alternativ­e to the state’s endless web of freeways and the carbon emissions generated.

Fourteen years later, constructi­on is underway on part of a 171-mile “starter” line connecting a few cities in the middle of California, which has been promised for 2030.

Meanwhile, costs have continued to escalate. When the California High-speed Rail Authority issued its new 2022 draft business plan in February, it estimated an ultimate cost as high as $105 billion. Less than three months later, the “final plan” raised the estimate to $113 billion.

The rail authority said it has accelerate­d the pace of constructi­on on the starter system, but at the current spending rate of $1.8 million a day, the train could not be completed in this century.

“We would make some different decisions today,” said Tom Richards, a developer from the Central Valley city of Fresno who now chairs the authority. He said project executives have managed to work through the challenges and have a plan that will, for the first time, connect 85% of California’s residents with a fast, efficient rail system. “I think it will be successful,” he said.

Unless rail authority managers can improve cost controls and find significan­t new sources of funding, they said, the project is likely to grind to a halt in future decades.

“I was totally naive when I took the job,” said Michael Tennenbaum, who was the first chair of the rail authority 20 years ago. “I spent my time and didn’t succeed. I realized the system didn’t work. I just wasn’t smart enough. I don’t know how they can build it now.”

The 2-hour, 40-minute dream

The goal in California in 2008 was to carry passengers between Los Angeles and San Francisco in 2 hours, 40 minutes, putting it among the fastest trains in the world in average speed.

The most direct route would have taken the train straight north out of Los Angeles along the Interstate 5 corridor through the Tejon Pass, a route known as “the Grapevine.” Engineers had determined in a “final report” in 1999 that it was the preferred option for the corridor.

But political concerns were lurking in the background. Mike Antonovich, a powerful member of the Los Angeles County Board of Supervisor­s, was among those who argued that the train could get more riders if it diverted through the growing desert communitie­s of Lancaster and Palmdale in his district, north of Los Angeles.

The extra 41 miles to go through Palmdale would increase costs by 16%, a difference in today’s costs of as much as $8 billion.

According to interviews with those working on the project at the time, the decision was a result of political horse-trading in which Antonovich delivered a multibilli­on-dollar plum to his constituen­ts.

The horse-trading involved an influentia­l land developer and major campaign contributo­r from Los Angeles, Jerry Epstein.

Epstein, who died in 2019, was a developer in the seaside community of Marina del Rey who was courting the Los Angeles County Board of Supervisor­s for a 40-year lease extension on a huge developmen­t.

Epstein, a member of the rail authority board, became a strong backer of Antonovich’s proposal for a Mojave Desert diversion on the bullet train.

“The Palmdale route was borne of a deal between Epstein and Antonovich, absolutely,” said Art Bauer, chief staff member on the State Senate Transporta­tion Committee.

The dogleg from Burbank to Palmdale was never without advantages. For one thing, said Richards, the current rail authority chair, the direct route through the Grapevine would have had higher land acquisitio­n costs and faced opposition by a major landowner. After the decision was made, Richards said, a follow-up study validated the choice.

But it has presented a complex engineerin­g challenge, requiring 38 miles of tunnels and 16 miles of elevated structures.

And it introduced a fundamenta­l conflict: If the train was to rush passengers between the state’s two urban hubs, how much speed should be sacrificed by turning it into a milk run across the huge state?

Then came the decision to start building a train between Los Angeles and San Francisco that reached neither city.

A bullet train for the Farm Belt

The idea of beginning constructi­on not on either end, but in the middle — in the Central Valley, a place few in Los Angeles would want to go — was a political deal from the start.

Proponents of running the rail through the booming cities of Bakersfiel­d, Fresno and Merced cited a lot of arguments: The Central Valley needed jobs. It would be an ideal location to test equipment. It would be the easiest place to build, because it was mostly open farmland.

But the entire concept depended on yet another costly diversion.

Instead of following Interstate 5 through the uninhabite­d west end of the valley, the train would travel through the cities on the east side — more passengers, but also more delays, more complicati­ons over acquiring land, more environmen­tal problems.

Rail authority leaders said starting the bullet train in the center of the state reflected a decision to make sure it served 85% of the residents of California, not just people at the end points. Running it on the east end of the valley, they said, would ensure that it served existing cities; building on empty farmland would encourage new sprawl.

“The key to high-speed rail is to connect as many people as possible,” Richards said.

Rail authority spokespers­on Annie Parker said studies in 2005 showed that building along the east side of the Central Valley provided better and faster service, although it was 6% more expensive. In any case, she said, the current route is what voters agreed to in 2008 in a $9 billion bond authorizat­ion.

State senators were under pressure to endorse the Central Valley plan, not only from Gov. Jerry Brown but also from President Barack Obama’s transporta­tion secretary, Ray Lahood, who came to the state Capitol to lobby the vote.

Which path through the mountains?

More political debate ensued over what route the train would take into the San Francisco Bay Area. The existing rail corridor through Altamont Pass, near Livermore, was a logical alternativ­e. French engineerin­g company Setec Ferroviair­e reported that the Altamont route would generate more ridership and have fewer environmen­tal impacts.

But as with so many decisions on the project, other considerat­ions won the day. There was heavy lobbying by Silicon Valley business interests and the city of San Jose, which saw the line as an economic boon and a link to lower cost housing in the Central Valley for tech employees. They argued for routing the train over the much higher Pacheco Pass — which would require 15 miles of expensive tunnels.

In 2008, the rail authority issued its record of decision.

“It absolutely has to go through Pacheco and up through San Jose,” Richards said.

 ?? RYAN CHRISTOPHE­R JONES / THE NEW YORK TIMES ?? Workers are seen Jan. 25 at a constructi­on site in Selma, Calif., for the state’s high-speed rail line. California’s monumental effort to build a high-speed rail system is at a crossroads. America’s first experiment with high-speed rail has become a multibilli­on-dollar nightmare — political compromise­s created a project so expensive that almost no one knows how it can be built as originally envisioned.
RYAN CHRISTOPHE­R JONES / THE NEW YORK TIMES Workers are seen Jan. 25 at a constructi­on site in Selma, Calif., for the state’s high-speed rail line. California’s monumental effort to build a high-speed rail system is at a crossroads. America’s first experiment with high-speed rail has become a multibilli­on-dollar nightmare — political compromise­s created a project so expensive that almost no one knows how it can be built as originally envisioned.
 ?? RYAN CHRISTOPHE­R JONES / THE NEW YORK TIMES ?? Cranes loom over a constructi­on site Jan. 25 in Fresno for California’s high-speed rail line.
RYAN CHRISTOPHE­R JONES / THE NEW YORK TIMES Cranes loom over a constructi­on site Jan. 25 in Fresno for California’s high-speed rail line.
 ?? Source: California High Speed rail Authority THE NEW YORK TIMES ?? Proposed High Speed Rail The California bullet train's route from Los Angeles to San Francisco, traversing the state's mountain ranges and its Central Valley, is shown in a dark black line. The route was selected over proposals that would have roughly followed the I-S and the 1.580 highways between Southern and Northern California. The light gray line shows a proposed second phase that would extend the system to San Diego and Sacramento, though it has not received environmen­tal approvals or funding.
Source: California High Speed rail Authority THE NEW YORK TIMES Proposed High Speed Rail The California bullet train's route from Los Angeles to San Francisco, traversing the state's mountain ranges and its Central Valley, is shown in a dark black line. The route was selected over proposals that would have roughly followed the I-S and the 1.580 highways between Southern and Northern California. The light gray line shows a proposed second phase that would extend the system to San Diego and Sacramento, though it has not received environmen­tal approvals or funding.