Las Vegas Review-Journal

Agency blamed for costs of suicide prevention net

- By Olga R. Rodriguez

SAN FRANCISCO — A suicide prevention net on San Francisco’s Golden Gate Bridge that is already years behind schedule will cost about $400 million, more than double its original price, because of problems sparked by the government agency that manages the span, the lead contractor­s allege.

The allegation­s filed Monday in state court by Shimmick Constructi­on Co. and Danny’s Constructi­on Co. say that changes to and flaws in the government’s net design and the lack of transparen­cy about the deteriorat­ion of the bridge’s maintenanc­e platforms have raised the constructi­on price from $142 million to at least $398 million.

“We were alarmed to discover the District concealed significan­t informatio­n during the proposal phase of the Project, including extensive deteriorat­ion in certain areas of the bridge,” Shimmick said in a statement.

The project aims to add 20-footwide stainless steel mesh nets on both sides of the 1.7-mile bridge and replace maintenanc­e platforms used by bridge workers that were built in the 1950s. Work on the net began in 2018 and was set to be completed by January 2021 but has been delayed.

Bridge officials in 2008 voted to move forward with the net, meant to deter those looking to jump to their deaths and catch those who do. Paul Muller, president of the Bridge Rail Foundation, a nonprofit created to end suicides on the bridge, said the span has been the site of nearly 2,000 suicides since it opened in 1937, including 25 last year alone.

The joint venture has completed about 47 percent of the net and expects to finish it by December 2023, nearly four years behind schedule. The upgraded platforms are not expected to be completed until January 2026.

Newspapers in English

Newspapers from United States