Los Angeles Times

MONEY COVERS BULLET TRAIN’S 1ST LEG

The state has enough funding to build the initial operating segment, but the future is uncertain.

- By Ralph Vartabedia­n

The state has enough money to build an initial operating segment of the bullet train from San Jose to the Central Valley but faces major uncertaint­ies about funding for the entire 500mile system and whether the initial system will be profitable, according to a new report by researcher­s for the Legislatur­e.

The California HighSpeed Rail Authority has identified the source of the $ 21 billion it says it needs for the f irst segment, said the report by the Legislativ­e Analyst’s Office.

But the project is $ 43.5 billion short of the total needed for the entire $ 64billion, 500- mile link from San Francisco to Southern California, the report said.

The analysis was conducted on the rail authority’s revised business plan, which was released last month.

Under the 2016 plan, the state would tap existing federal grants, the sale of bonds approved by voters in 2008 and greenhouse gas fees to build the $ 21- billion initial segment.

But funding for the rest of the project is unidentifi­ed, the report said.

Analysts noted that the use of greenhouse gas fees would extend only until 2020, when the fund- generating program is set to expire. The fees this year are providing an estimated $ 600 million for the project, and the rail authority ultimately wants approval to borrow against future fees.

The report also noted that state law will allocate an additional $ 400 million from the greenhouse gas fees that the Legislatur­e previously borrowed for the general fund.

The rail authority’s busi-

ness plan says private investors will eventually help fund additional constructi­on for the full system, based on future profits from operating a partial segment.

But legislativ­e analysts raised concerns about that projection, saying “it is unclear whether the system will actually generate an operating surplus.”

Even with private funding the project would be “significan­tly short of the level needed” to complete the San Francisco- Southern California system,” analysts said. The plan “does not identify how this shortfall would be met,” they said.

The report also warned that the southern terminus of the initial segment would be north of Bakersfiel­d in what is now an agricultur­al field.

“Even with a temporary station or platform, ending the [ initial operating segment] in an unpopulate­d agricultur­al area does not appear to be an effective approach,” the report said.

“This is because this location would not have the types of facilities and nearby businesses, such as transit connection­s, rental car facilities and shops necessary to meet the needs of train passengers.”

Still, the report said current plans to build an initial segment from San Jose to the Central Valley, rather than from Burbank to the Central Valley under previous business plans, has “merit” and faces “less risk” because it would f it within its existing funding and be less technicall­y difficult because it avoids crossing the mountains north of Los Angeles.

In a response to the report, the rail authority did not address specific issues but said: “The LAO report f inds merit in the Central Valley to Silicon Valley segment proposed in the 2016 Draft Business Plan. We remain committed to moving forward with this project to create jobs, improve air quality and better connect California’s communitie­s.”