Los Angeles Times

Spillway fix faces tight deadline

Engineerin­g expert doubts that repairs at Oroville Dam will be finished by start of next rainy season.

- By Joseph Serna joseph.serna@latimes.com

An engineerin­g expert who visited the troubled Lake Oroville reservoir said this week that it would be nearly impossible for the state to complete temporary repairs to its fractured and eroded main spillway by a target date of Nov. 1.

In a report submitted to the Federal Energy Regulatory Commission this week, a panel of five independen­t consulting engineers warned that “a significan­t risk would be incurred” if the main spillway was not operationa­l after October, which is the traditiona­l start of California’s rainy season.

However, an engineerin­g and risk management expert who was not part of the consulting panel told The Times this week that he doubted the state could meet such a close deadline.

“I think that is a challengin­g timeline,” said Robert Bea of UC Berkeley’s Center for Catastroph­ic Risk Management.

Bea, a retired civil engineerin­g professor who led an investigat­ion into failure of the New Orleans levee system after Hurricane Katrina, visited the reservoir recently to review inspection documents, as well as the report by the Independen­t Board of Consultant­s. The consultant­s proposed that temporary repairs to the spillway be completed by Nov. 1, and that permanent repairs be completed after the rainy season.

In order to accomplish this, report authors said the Department of Water Resources should award grading contracts by March 31, complete design plans by mid-May and approve a constructi­on contract by June 1. That would give the company five months to complete the work, the report suggested.

Bea said that schedule leaves little space for unanticipa­ted problems.

“Previous experience with these kinds of ‘rushed’ field constructi­on projects clearly indicates — expect the unexpected,” Bea said. “There will be delays that result in extension of optimistic schedules.”

According to department spokeswoma­n Lauren Bisnett, the agency is still formulatin­g a plan of action.

“We are in the process of analyzing alternativ­e approaches, both temporary and permanent, and we expect to detail that process and preferred alternativ­es within the next weeks,” Bisnett wrote in an email Friday.

She said the agency was committed to completing the job on time.

“DWR has stated from the beginning that our objective is to have a fully functional spillway before the start of the next storm season — response and recovery efforts are being expedited to make that happen.” Bisnett wrote.

The spillway, although not part of Oroville Dam itself, is the primary means of releasing water from Lake Oroville in a controlled fashion. Without it, water levels would steadily rise until the reservoir overflowed and flooded the Feather River and nearby communitie­s.

A steeply sloped stretch of concrete some 3,000 feet long, the main spillway is as wide as a four-lane highway. Water released from the reservoir can speed along the channel at more than 50 miles per hour, and the force it exerts on the concrete is tremendous.

After half a century of service, those forces finally hammered through the spillway’s concrete deck and caused a major crisis in February, when more than 100,000 area residents were evacuated.

Since then, the Department of Water Resources has scrambled to shore up and stabilize erosion at the main spillway and an earthen emergency spillway.

The agency has also had to perform a delicate balancing act as it alternates between conducting repairs to the main spillway and using it to release runoff from a record season of rain and snow. The result has been a yo-yo effect with the reservoir’s water level.

Bill Croyle, acting director for the agency, estimated that crews may have to release water down the main spillway two more times before June.

Newspapers in English

Newspapers from United States