Los Angeles Times

COST FOR BULLET TRAIN JUMPS SHARPLY

Rail authority says tab for connecting L.A. to San Francisco is now $77.3 billion and could soar even further.

- By Ralph Vartabedia­n

The price of the California bullet train project has risen sharply, with the state rail authority announcing Friday that the cost of connecting Los Angeles to San Francisco would be $77.3 billion and could rise as high as $98.1 billion — an uptick of at least $13 billion from estimates two years ago.

The authority also said the earliest that trains could operate on a partial system between San Francisco and Bakersfiel­d would be 2029 — four years later than the previous projection. The full system would not begin operating until 2033.

The disclosure­s are contained in a 114-page business plan issued in draft form Friday by the rail authority before public hearings and formal submission to the Legislatur­e in about 60 days.

The new estimates will force California’s leadership to double down on its political and financial commitment­s if it wants to see the system completed, against a backdrop of rising costs, years of delays, strident litigation and backlashes in communitie­s where homes, businesses, farms and environmen­tal preserves will have to give up land to the rail’s right-of-way.

The rail authority has wrestled with a more than $40-billion funding gap, which would increase further under the new cost estimates. It is still counting on the Legislatur­e to amend the state’s greenhouse gas auction system so that the system could borrow against future fees through 2050, but even with that benefit the project faces a financial shortfall that only partnershi­ps with the federal government and private investors could plug, said rail

authority chief executive Brian Kelly.

The new business plan is based on a wide range of uncertaint­ies, Kelly said. Among the most challengin­g is the cost of about 36 miles of tunnels through mountainou­s Southern California, which could range anywhere from $26 billion to $45 billion, according to the report. “These are the best estimates we have to date,” Kelly said.

The rail authority could reduce costs and risks, Kelly said, if there were greater certainty about future funding. In a best-case scenario, the business plan projects costs as low as $63.2 billion. Kelly said building a megaprojec­t like the bullet train is not possible with a “pay as you go” approach.

The reaction to the business plan was less than enthusiast­ic, even from Democrats who have long backed it as a way to revolution­ize transporta­tion in the state while reducing emissions.

“At first glance, the High Speed Rail project is still over budget and the funding to complete the program hasn’t been identified,” said Jim Frazier (D-Discovery Bay), chairman of the Assembly Transporta­tion Committee, which will hold an oversight hearing on the plan on April 2. “We still have no realistic way to pay for the project.”

Republican­s were predictabl­y harsher.

“Initially a rathole, now a sinkhole, soon it will be an abyss in which more and more tax dollars are forever lost. I speak of the neverendin­g scam called High Speed Rail,” said Sen. Andy Vidak (R-Hanford).

A spokesman for Gov. Jerry Brown, who since the 1980s has championed highspeed rail, said the disclosure­s do not change the strong support he expressed in his recent State of the State address, when he said: “I make no bones about it. I like trains, and I like highspeed trains even better.”

The projection for completing the full Los AngelesSan Francisco system by 2033 assumes that somehow the project gets fully funded. Even then it is extremely ambitious given the engineerin­g challenge of building across the San Gabriel and Tehachapi mountains and the developed stretch from Santa Clarita to downtown Los Angeles, as well as more than one mile under urban San Francisco — all in just four years after the initial system starts operating.

The biggest immediate driver of the cost increase has been in the Central Valley, where the rail authority is building 119 miles of track between Wasco and Madera. The authority disclosed in January that the cost of that work would jump to $10.6 billion from an original estimate of about $6 billion. Roy Hill, one of the senior consultant­s advising the state, told the rail authority board, “The worst-case scenario has happened.”

The business plan incorporat­es those cost increases, but it also has more money in contingenc­y accounts for future setbacks and includes more for future inflation, Kelly said. One of the top priorities now, Kelly said, is to fulfill the state’s obligation­s under $3.5 billion in grants that the Obama administra­tion provided, which require that 119 miles of track be completed and all of the project’s environmen­tal clearances be obtained by 2022. The federal government could theoretica­lly ask for its money back if those requiremen­ts are not met, officials close to the project say.

The plan also appears to assume that the Central Valley increases are not predictive of what will happen along other segments. The plan projects a cost of $29.5 billion to build an initial operating segment from a station in San Francisco to Bakersfiel­d, a longer starter system than the previous plan had at $21 billion. Apart from that $8.5 billion increase, the new plan has just $4.6 billion in other increases that would apply to the rest of the route, even though the fouryear delay in completion will add inflationa­ry costs.

In its 2014 business plan, the rail authority optimistic­ally projected it could begin carrying passengers in just seven years. But the warning signs of uncontroll­ed cost growth had already started mounting.

The project issued its first constructi­on contract in 2013, when it had almost no property and was experienci­ng trouble acquiring more. Lawsuits filed by counties, water agencies, farm bureaus and cities did not stop the project, but caused delays and sharply drove up costs.

The cost of environmen­tal reviews jumped from a projected $388 million in 2010 to more than $1 billion.

The rail authority found that nobody could be sure what was under the ground in Fresno, driving up the cost of relocating sewers, water lines and electrical conduits by hundreds of millions of dollars.

The disclosure about the higher costs comes nearly a decade after voters approved a $9-billion bond to build a bullet train system. The original idea was that the federal government would pay about a third of what was then an estimated $33-billion project, with private investors covering another third.

But those assumption­s proved faulty on numerous counts. In later business plans the projected cost went to $43 billion, somewhere between $98 billion and $117 billion, down to $66 billion, and then to $64 billion in 2016. And the funding sources dried up. The federal government put in only $3.5 billion and Republican­s have vowed not to add another penny. Private investors have said they would not commit any investment to the project without a guarantee that they can’t lose money.

The business plan devotes an entire chapter to reviewing its past mistakes and proposing solutions so that they are not repeated. For example, the rail authority says it will not issue future constructi­on contracts until it has acquired all the land beforehand.

Despite the challenges, supporters point to the 1,700 constructi­on jobs it has created in the economical­ly depressed Central Valley and the environmen­tal benefits of an electric transporta­tion system that is supposed to haul millions of people.

“We now have a new plan with the right man in the right place at the right time for the right job,” Robbie Hunter, president of the State Building & Constructi­on Trades Council of California, said of Kelly. “This project is critical to handle a California population that is growing toward 50 million.”

Rail officials said they remain hopeful the project will attract private money.

 ?? California High-Speed Rail ?? A WORKER on the rail project ties rebar inside a column at the Cedar Viaduct.
California High-Speed Rail A WORKER on the rail project ties rebar inside a column at the Cedar Viaduct.

Newspapers in English

Newspapers from United States