$545 million flood control project launches

Three-phase project addresses increasing threats from S.F. Bay sea level rise

- By Paul Rogers progers@ bayareanew­sgroup.com

San Francisco Bay is famous worldwide for the Golden Gate Bridge, Alcatraz and many of the tech companies that ring its edges.

But increasing­ly, scientists and political leaders are realizing the bay is more than a scenic wonder: It's also an increasing­ly serious threat to millions of residents and hundreds of billions of dollars of bay front property — from neighborho­ods to freeways to airports — as seas continue their slow but relentless rise.

On April 14, state, federal and local leaders broke ground on the latest effort to reduce that risk, kicking off a $545 million project to protect San Jose's shoreline against winter flooding and rising sea levels from climate change.

The project, led by the Army Corps of Engineers, will construct 4 miles of engineered earthen and clay levees 15 feet high near Alviso and restore 2,900 acres of former Cargill industrial salt evaporatio­n ponds back into tidal wetlands, which helps slow wave energy in storms and provides habitat for fish and wildlife.

The new levees will replace old dirt berms that are 6 feet to 10 feet high, offering more protection from flooding for areas north of Highway 237, including key facilities such as the region's wastewater treatment plant, rail lines and the homes of 5,500 people.

“Climate change is real,” said Col. Antoinette Gant, division commander with the U.S. Army Corps of Engineers regional office in San Francisco. “That means there has to be changes. We can't do the same things we have done for years and years. We've got to continue to make progress.”

San Francisco Bay has risen by 8 inches in the past 100 years, according to the tidal gauge at Fort Point under the Golden Gate Bridge and other instrument­s. As the planet continues to warm, melting ice caps and expanding the volume of seawater, scientists project bay waters will rise another 1 feet to 2 feet by 2050 and 5 feet to 7 feet by 2100.

“We've built megacities of the world on coasts,” said Gary Griggs, a distinguis­hed professor of earth sciences at UC Santa Cruz. “We didn't think of sea level rise 100 years ago, and now we are having to pay the price. Whether it is Jakarta or Miami or San Francisco, they all have the same problems.”

The South San Francisco Bay Shoreline project, which has been hamstrung

by cost overruns and delays, is the latest major effort to deal with the increasing flood threats around the bay.

Others include a $5 billion project to rebuild the massive seawall along San Francisco's Embarcader­o from Fisherman's Wharf to the Giants ballpark, where flooding is increasing­ly common during big storms; a $587 million project to build higher levees around San Francisco Internatio­nal Airport to keep the runways from flooding during high tides and storms; and a $4 billon proposal to raise Highway 37 in the North Bay.

The South Bay project is divided into three massive phases.

Constructi­on on the first half of Phase 1 is expected to continue until January 2024. Levee work will extend from Alviso Marina County Park to Artesian Slough near the San Jose-santa Clara Regional Wastewater Facility, a plant that serves 1.4 million people in eight cities and is at high risk of flooding.

Like New Orleans, the community of Alviso sits

below sea level from overpumpin­g of groundwate­r generation­s ago that caused the ground to sink. It has flooded multiple times in the past 75 years.

The second half of Phase 1 will increase flood protection from Artesian Slough east to Coyote Creek. It is on hold while constructi­on planning, access points, haul routes, staging and easements are still being worked out.

The project is a partnershi­p between the Army Corps, the Santa Clara Valley Water District and the state Coastal Conservanc­y. Planning is underway for Phase 2 and Phase 3, which eventually will provide similar flood protection north to Sunnyvale, Mountain View and Palo Alto sometime after 2030, likely at a cost above $1 billion.

Environmen­tal groups say the project is critically needed. But they have criticized the Army Corps

of Engineers for moving too slowly. The corps first agreed with the water district on the project in 2005.

“The project is essential,” said David Lewis, executive director of Save the Bay, an environmen­tal group based in Oakland. “The only problem is that it has taken so long and gotten so expensive.”

Lewis said that regional planners, led by the Bay Conservati­on and Developmen­t Commission, a state agency, have not done enough to coordinate bay front developmen­t and flood protection with cities and the nine counties in the Bay Area. Also, tech companies, including some of the wealthiest in the world whose headquarte­rs will benefit from the flood protection, such as Google, have not contribute­d to the costs.

The Bay Area is further ahead in addressing sea

level rise than many other regions of the world. But the costs are expected to be immense.

Of the $545 million price tag for Phase 1 of the project, $124 million came from the federal government, $61 million came from Measure AA, a $12-per-year parcel tax passed by Bay Area voters in 2016 for flood control, and the rest is the water district's responsibi­lity. The price tag tripled from original estimates several years ago after the Army Corps underestim­ated the cost of the levee materials and the prices went up.

But for officials, finally seeing heavy equipment on the waterfront was a cause for celebratio­n.

Dick Santos, an Alviso native whose home flooded three times since the 1950s, said the work was a long time coming.

“I wish my dad was here to see it today,” Santos said. “He would be pleased.”

 ?? PHOTOS BY ARIC CRABB — STAFF PHOTOGRAPH­ER ?? California Secretary for Natural Resources Wade Crowfoot, left, takes a photo with Lt. Col. Kevin Arnett of the U.S. Army Corps of Engineers, second from left, and other local leaders after a groundbrea­king ceremony for the South San Francisco Bay Shoreline Project at Alviso Marina County Park in San Jose on April 14.
PHOTOS BY ARIC CRABB — STAFF PHOTOGRAPH­ER California Secretary for Natural Resources Wade Crowfoot, left, takes a photo with Lt. Col. Kevin Arnett of the U.S. Army Corps of Engineers, second from left, and other local leaders after a groundbrea­king ceremony for the South San Francisco Bay Shoreline Project at Alviso Marina County Park in San Jose on April 14.
 ?? ?? Constructi­on equipment for the South San Francisco Bay Shoreline Project is photograph­ed along Pond A12at Alviso Marina County Park on April 14 in San Jose. Phase 1of the flood control project is scheduled to be completed in January 2024.
Constructi­on equipment for the South San Francisco Bay Shoreline Project is photograph­ed along Pond A12at Alviso Marina County Park on April 14 in San Jose. Phase 1of the flood control project is scheduled to be completed in January 2024.