Morning Sun

MULTI-YEAR VELSICOL CLEANUP CONTINUES

DDT, PBB among chemical hazards being addressed in longtime remediatio­n effort

- By Greg Nelson gnelson@medianewsg­roup.com

Remediatio­n of the former Velsicol Chemical Co. plant site in St. Louis will likely take several more years before it’s finished.

The facility closed in 1978 following the well-documented PBB disaster, then was completely demolished and buried on the now vacant and contaminat­ed 52-acre parcel.

It’s estimated that more than $150 million has been spent on the cleanup thus far and that figure could reach a half-a-billion dollars by the time it’s complete.

On-site groundwate­r is contaminat­ed with DDT, chlorobenz­ene, carbon tetrachlor­ide and other chlorinate­d compounds. In addition, the soil contains PBB, copper, chromium, zinc and magnesium. For the past three years the U.S. Environmen­tal Protection Agency and Michigan Department of Environmen­t, Great Lakes and Energy have been using thermal treatment technology to heat the soil and groundwate­r on small sections of property, capture the contaminan­ts and treat them on-site.

The agencies have also been collecting NAPL, or non-aqueous phase liquid, from extraction wells throughout the heating process.

Thus far about 135,000 pounds have been removed during phase 2 on a 1.5-acre parcel known as Area 2.

The NAPL consists of about 80 percent DDT, which was expected.

Although recovery has slowed, the heating process, which EPA officials had hoped would be completed by now, has been extended until at least mid-january, according to EPA Project Manager Tom Alcamo.

The first phase of Area 2 was completed last year with 183,000 pounds of contaminan­ts and more than 4 million gallons of polluted groundwate­r removed.

The treatment costs about $800,000 a month and another $1.2 million has been built into the project to cover the additional time required, Alcamo told members of the Pine River Superfund Citizen Task Force during a recent meeting.

More than 11.5 million kilowatts of electrical energy was used to heat the soil in phase 1 of the Area 2 cleanup.

However, getting trucks to transport the contaminat­es, incinerato­r slots at an out-of-state landfill and shipping costs are proving to be a challenge for the agency, Alcamo noted.

Hazardous waste from most of the Velsicol projects is taken to a Clean Harbors incinerati­on facility in Arkansas.

Additional work is already being planned for next year, according to EPA Community Involvemen­t Coordinato­r Diane Russell.

The EPA and EGLE “continue to work on design studies for future cleanup activities that will take place at the former chemical plant site,” she said.

“EPA expects the next constructi­on will begin next spring or summer in which approximat­ely 100,000 tons of contaminat­ed soil will be excavated and

disposed of off-site in an approved landfill. This work will likely continue for over two years.”

However, during that portion of the project strong odors due to the presence of petroleum products could become an issue.

Because volatile organic compounds will be part of

the excavation, air monitoring will take place, Alcamo said.

But the good news, he noted, is that dibromochl­oropropane, a pesticide banned by the EPA for most agricultur­al uses in 1979, is not present on the property.

 ?? GREG NELSON — MORNING SUN ?? Remediatio­n of the former Velsicol Chemical Co. plant site in St. Louis is continuing but will likely take several more years and millions of dollars before it’s finished.
GREG NELSON — MORNING SUN Remediatio­n of the former Velsicol Chemical Co. plant site in St. Louis is continuing but will likely take several more years and millions of dollars before it’s finished.

Newspapers in English

Newspapers from United States