Bella Vista, 412 bypasses on schedule

Officials say Missouri dealing with cash shortage

- RON WOOD See BYPASSES, Page 4B

FAYETTEVIL­LE — Work on Bella Vista and U.S. 412 bypass projects is on or ahead or schedule thanks to good weather, state highway officials said.

“We’ve had quite a bit of rain, but they’ve still been able to work quite a bit,” said Mitchell Archer, District 9 constructi­on engineer. “We’re working out our issues as we go through.”

Work continues on the 14-mile Bella Vista Bypass even though Missouri highway officials said they don’t have the money to link up with the new road at the state line, as has long been the plan.

Work is ongoing from Interstate 49 in north Bentonvill­e, including a large roundabout and other interchang­e improvemen­ts. The road will be part of I-49 when completed. Base and concrete paving are in place from Arkansas 72 on the west to past Pumpkin Hollow Road, going east.

“Realistica­lly, we’re looking at right after the first of the year before we’ll actually be opening the roundabout and sending traffic down the new bypass,” Archer said. “There’s going to be a lot of the work that will be completed, but once you

complete that bulk work, there’s a lot of cleanup, there’s a lot of shoulder gravel to put on, you have to pave the shoulders with asphalt.”

The Bella Vista Bypass is designed to route traffic around the western edge of Bella Vista near I-49’s exit 93, rejoining I-49 near Pineville, Mo. The road is expected to take up to 6,000 cars a day off U.S. 71 through Bella Vista.

Archer said the department measures progress by comparing percentage of time allotted for a job to the percentage of the job completed. Bella Vista Bypass jobs were allotted 257 working days and crews have worked 236 days. Archer said the contractor has used 94.4 percent of the time, and 78 percent of the money for current work has been used. The money side is catching up pretty quickly because crews are doing some of the more high-dollar work now.

The roundabout cannot be opened until the road is completed to basically the Arkansas 72 interchang­e, Archer said.

Getting the road connected back to I-49 in Missouri still requires Arkansas building a 2.5-mile section to the state line and Missouri building a section from the state line to just south of Pineville.

Darin Hamelink, area engineer for the Missouri Department of Transporta­tion, told regional planners earlier this year $20 million is budgeted in 2020 for constructi­on of the 4.81-mile project, but another $30 million is needed to finish the road.

All right of way has been acquired, Hamelink said. He said the environmen­tal impact statement needs to be done. Preliminar­y design work is completed, but $3 million must be allocated to finish the plans, he said.

Missouri officials, at one time, said they had money in hand to go ahead with the project when Arkansas was ready. Arkansas wasn’t ready at that point and Missouri switched the money to other projects. Hamelink said Missouri is now dealing with a shortage of highway money.

“I don’t think we’ll ever see constructi­on quit on the Bella Vista Bypass until it’s four lanes and finished,” said Dick Trammel, chairman of the Arkansas Highway Commission. “It’s not a road to nowhere. The part that’s finished and open, it’s being used pretty heavily.”

To the south, work on the U.S. 412 Northern Bypass around Springdale between Arkansas 112 and I-49 started in April 2015 and is expected to be completed in 2019. The project was the most expensive job in Highway Department history when it was let at just more than $100 million.

Contractor­s earlier this week were at 289 of 650 working days, putting them at 44.5 percent of the time allotted for the job, but they’re at 51.7 percent of the work done so they’re ahead of schedule at this point, Archer said.

The 412 Northern Bypass is intended to relieve congestion through Springdale on Sunset Boulevard, South Thompson Street and Robinson Avenue, the city’s main east-west route, which is designated U.S. 412. Traffic studies say about 25,000 vehicles a day travel the route, according to highway officials.

“You can see the work on the two flyover bridges that’s going on in the median of I-49. That work is progressin­g,” Archer said. “The tie-in at Arkansas 112 is progressin­g,” he said.

The work includes widening Arkansas 112.

“We probably won’t see any traffic shifts over onto the new bridge until about the end of the year, but we are shifting traffic to allow for staged constructi­on of the interchang­e.”

The new bridge to carry Arkansas 112 over the bypass is built, but needs the parapet walls placed, Archer said.

The 4-mile section will provide a jumping off point for a planned limited access highway to the Northwest Arkansas Regional Airport.

The bypass will curve back south and connect to U.S. 412 on the west side of Springdale near Tontitown. The eastern half of the bypass should eventually connect to U.S. 412 near Sonora, east of Springdale, but that part of the project is not funded.

 ?? NWA Democrat-Gazette/BEN GOFF @NWABENGOFF ?? Work continues Thursday on the new interchang­e for the Bella Vista Bypass at the intersecti­on of Interstate 49 and North Walton Boulevard in Bentonvill­e.
NWA Democrat-Gazette/BEN GOFF @NWABENGOFF Work continues Thursday on the new interchang­e for the Bella Vista Bypass at the intersecti­on of Interstate 49 and North Walton Boulevard in Bentonvill­e.