Northwest Arkansas Democrat-Gazette

Lockheed ships nearly year late

Production, workforce problems cited for delays in delivery

- TONY CAPACCIO

Lockheed Martin Corp. will deliver its eight remaining littoral combat ships an average of 11 months late, more than twice the five-month delay for rival shipbuilde­r Austal Ltd., the U.S. Navy estimates.

The contractor­s build different versions of the ship that’s been criticized for rising costs, equipment breakdowns and potential vulnerabil­ity in combat. Now, Austal’s timelier performanc­e may give the Australian company an advantage in the winner-takeall competitio­n for a guidedmiss­ile frigate intended as a more robust successor.

The delays also postpone availabili­ty of the vessels for a Navy that says it’s hobbled by readiness shortfalls and a shortage of ships that officials say will be solved over time if the service expands to 355 vessels from 279 today.

The Navy attributed the delays for Bethesda, Md.-based Lockheed to past or recently resolved issues in production and maintainin­g the shipyard workforce. The 11-month average delay is an increase from an average of about five months that the Naval Sea Systems Command estimated in March in response to an inquiry.

The most recent Lockheed ship, the USS Little Rock, was delivered on Sept. 25 — 13 months past its contracted delivery date, the Navy said in an email. It was stymied for months by faulty propulsion­system gears from a German subcontrac­tor that have been resolved, according to the service.

The Naval Sea Systems Command estimates the next three Lockheed vessels — the USS Sioux City, Wichita and Billings — will be delivered in January, June and December 2018. Navy budget documents in February 2016 had projected the deliveries for February and July of this year and February of 2018.

The Sioux City’s delivery delay “was caused by correction of shipbuilde­r-responsibl­e deficienci­es,” the sea systems command said in an email.

Deliveries of the remaining seven vessels by Austal, which builds a trimaran version of

the littoral combat ship, are “projected to remain stable to revised schedules,” the command said.

The USS Little Rock (LCS 9) will be commission­ed Saturday in Buffalo, N.Y. The ceremony will take place beside the older USS Little Rock, which served as a light cruiser and then a guided missile cruiser. It is now a 610-foot-long floating museum that draws roughly 70,000 visitors per year.

The original USS Little Rock was in service from August 1944 until being decommissi­oned in November 1976. It is on display at the Buffalo and Erie County Naval and Military Park at Canalside.

The Navy plans to spend $21 billion on the littoral combat ship program. At least $17.4 billion has been approved by Congress to date. Lawmakers working on spending bills for the current fiscal year are considerin­g approving as many as three more of the ships, or one more than requested by President Donald Trump’s administra­tion.

Lockheed’s “constructi­on durations and delivery dates were driven by the start-up of serial production” at its Fincantier­i Marinette Marine subcontrac­tor, which is building the vessels in Wisconsin, the Navy said. The Lockheed program also has “realized delays as a result of a now-corrected” gear deficiency as delivery dates “are now projected to remain stable,” the Navy said.

Part of the problem is “due to a lack of skilled labor,” according to a Pentagon informatio­n paper prepared in late October for a meeting with Lockheed officials.

“We are committed to ensuring all” vessels “are designed and built to the highest quality standards. With each ship produced our team is increasing efficiency and working to drive down costs and improve capability,” Lockheed spokesman John Torrisi said in an email.

He said the USS Little Rock was delivered to the highest quality score of any of the contractor’s littoral combat ships to date, based on its at-sea builder’s trial. The Sioux City is sailing in its builder’s sea trial and is on schedule for an early 2018 delivery, he said.

Austal spokesman Michelle Bowden said its production line in Mobile, Ala., “is mature and stable” and the company is “on schedule to deliver four” of its next ships in 24 months.

The Navy frigate program is proceeding in two phases. A current request for proposals has been issued for conceptual design contracts to be awarded this fiscal year. That will be followed by the winner-take-all constructi­on contract in 2020. In addition to Lockheed and Austal, General Dynamics Corp.’s Bath Iron Works unit said it will evaluate the request for proposals in partnershi­p with Navantia SA of Spain. Responses are due Dec. 18.

“Past performanc­e is one of five evaluation factors, along with technical approach, management approach, facilities, and price,” Ronald O’Rourke, naval analyst for the Congressio­nal Research Service, said in an email.

Still, Shelby Oakley, director of shipbuildi­ng for the Government Accountabi­lity Office, said in an email that it’s “not clear that LCS delays are significan­t to the frigate program.”

 ?? AP ?? The new USS Little Rock, a littoral combat ship built by Lockheed Martin, arrives Dec. 4 at the Buffalo, N.Y., harbor. Its delivery to the Navy in September was 13 months late.
AP The new USS Little Rock, a littoral combat ship built by Lockheed Martin, arrives Dec. 4 at the Buffalo, N.Y., harbor. Its delivery to the Navy in September was 13 months late.

Newspapers in English

Newspapers from United States