Northwest Arkansas Democrat-Gazette

Lack of money for reactor cleanup could halt work

Crews expected to maintain ‘periodic’ presence at test site owned by UA

- JAIME ADAME

FAYETTEVIL­LE — Work to clean up a nuclear reactor test site owned by the University of Arkansas will come to a halt by the end of this month due to a lack of money, said Mike Johnson, UA’s associate vice chancellor for facilities.

But he said it’s possible a request for $8 million from the federal government will come through to allow for the project’s completion over the next 12 months. Crews are expected to maintain a “periodic” presence after April 1, he said, and there’s a plan allowing for a restart with 45 days notice to begin removing the facility’s radioactiv­e reactor core.

Located about 20 miles southwest of Fayettevil­le, the Southwest Experiment­al Fast Oxide Reactor, often referred to as SEFOR, ceased operations in the early 1970s, with UA taking over ownership in 1975.

A $10.5 million U.S. Department of Energy grant, announced in October 2016, helped jump-start remediatio­n of the site in rural Washington County. Thousands of pounds of low-level radioactiv­e waste have since been trucked away to a specialize­d disposal facility in Utah.

Johnson and officials with nuclear services company Energy Solutions will host a community meeting at 6 p.m. today at the Strickler Volunteer Fire Department to go over the latest project details.

“We still believe that there remains a slight chance of additional FY 18 funds,” Johnson said in an email Wednesday, referring to the federal fiscal year which extends through September.

The request for $8 million would bring the total project cost to $24 million, he said.

After April 1, the plan is for staff with UA or Utah-based Energy Solutions to visit the site likely every week, Johnson said. Radioactiv­e material licenses would remain in place and some storage of equipment would continue, he said.

The cost this month in transition­ing to what Johnson referred to as SAFSTOR status — a term defined by the U.S. Nuclear Regulatory Commission as a method of decommissi­oning that involves a facility being safely stored to be decontamin­ated later — is about $60,000, he said.

Costs beginning April 1 would be about $4,000 per month for up to 12 months, with it then costing about $175,000 to restart cleanup with 45 days notice, he said.

“Contract modificati­ons are currently underway to make these firm numbers,” Johnson said, referring to work with Energy Solutions, the company overseeing the cleanup.

A more complete pullback would have meant “significan­t additional risk management responsibi­lities” for the university as well as additional financial costs for restarting work, Johnson said.

The reactor was built in 1968 with money from what was known as the U.S. Atomic Energy Commission. It was never hooked up to any turbine machinery so no electricit­y was produced.

The University of Arkansas took over ownership of the site in 1975 for use as a research tool for graduate students.

Fuel used in the reactor was removed from the site after it ceased operating, Dean Wheeler, the Energy Solutions project manager for the SEFOR cleanup, said during a public tour of the site in January 2017.

The tour, attended by roughly 400 people, offered the public a rare glimpse at a site that, by 1986, had fallen out of use.

UA has long sought federal aid to clean up the site. The university previously estimated the total project cost to be $26.1 million. In 2009, UA was awarded a federal planning grant of $1.9 million, and, after the U.S. Department of Energy grant announceme­nt in 2016, the university has received about $5 million from a federal appropriat­ions bill.

Johnson said there are no available university resources to help pay for the cleanup, and the university “would not expect that to be a future considerat­ion.”

Newspapers in English

Newspapers from United States