Council members hear update on bond projects

- LAURINDA JOENKS

SPRINGDALE — The city spent $1.6 million the last week of September and $2 million the first week of October — all on bond projects, Wyman Morgan told City Council members Tuesday night.

Morgan, the city’s director of finance and administra­tion, said the city in September spent $19 million in 2018 bond money.

“And everything is balanced and accounted for,” Morgan said.

Voters approved a $220 million bond issue in February 2018 providing money for street projects, the Fire Department, a new animal shelter, parks and recreation facilities and a new city administra­tion complex. With nothing else on the agenda for Tuesday’s meeting, the department heads over those areas gave council members progress updates.

Sixteen street projects are completed or in various stages, said Brad Baldwin, director of engineerin­g and public works.

“We started with 30-some possible projects and asked for public input. Then you prioritize­d the projects,” he said.

A Gene George Boulevard extension north to Elm

Springs Road is under constructi­on and expected to be completed in June. Maple Avenue’s extension east to Park Street will begin this month, Baldwin said.

Projects nearing the constructi­on phase include improvemen­t to 40th Street north of Falcon Road to the Arkansas Game & Fish Commission’s nature center — also is under constructi­on; Ford Avenue’s extension from the industrial park to Butterfiel­d Coach Road; and 56th Street south to Johnson.

Baldwin said most projects have cost less than budgeted, but he sees costs increasing as new bids arrive.

Mayor Doug Sprouse said the city waits for final bids on several of the projects before choosing others. He listed George Boulevard north to Bob Mills Road or even County Line Road as an important project. “As is extending Don Tyson Parkway east to (U.S.) 412. Or you may know of others. You will need to decide,” he told the council.

Morgan said the city has $67 million in highway projects underway, with $13 million held in reserve. He expects the city

to retain $6 million to put into other projects after contracts are signed as final bids are approved.

Fire Chief Mike Irwin said Fire Station No. 7 is open and fully operationa­l.

The new station on Har-Ber Avenue opened in July. Irwin said the project also was completed about $117 million under budget.

“At Station No. 8, they just poured the concrete under the apparatus bay,” Irwin said, referring to the garage area to hold the station’s vehicles. He said $960,168 of the $3.172 million planned for Station No. 8 has been spent, but he also expects the project to come in under budget. The station will serve the city’s industrial parks from East Huntsville Avenue.

The department has paid the park bond fund $33,125 for land where it will sit in the new Shaw Family Park in the far northweste­rn reaches of the city, Irwin said.

Bond money also has been used to expand the fire training center, buy equipment and pay for a radio system for the Fire and Police department­s.

Irwin said he expects about $400,000 will remain in the fund after all promised projects are completed.

“But don’t worry. We’re not going to give it back to you,” Irwin joked with the council.

Sprouse suggested using the money to buy the property behind the department’s Station No. 4 on Elm Springs Road. In fact, the city has started an appraisal process, he said.

“That’s the next station for expansion,” Sprouse said. “It’s in a great location.”

The city will break ground on Shaw Park on Oct. 21, said Chad Wolf, Parks and Recreation Department director.

The city spent $474,000 for the park’s design. The bond’s other big project — renovating Randal Tyson Recreation­al Complex — rests with the designers. The city capped the project at $5 million, which should pay to update the park to compliance with the Americans With Disabiliti­es Act and new lighting for some of the baseball fields, Wolf said.

The city spent $4.1 million of the $21 million park bond money to buy its recreation center, known variously as the former All-Star or Next Level building. The building — purchased in December — still needs a new heating and air conditioni­ng system — which will cost about $1 million, Wolf said.

The city will look to other sources of money for the repairs, Sprouse said.

 ?? NWA Democrat-Gazette/DAVID GOTTSCHALK ?? Rufus, a dog owned by Courtney Kremer, director of Animal Services for Springdale, participat­es Tuesday in the groundbrea­king for the new Animal Shelter and Adoption Center for Springdale. The new facility, at 1549 E. Don Tyson Parkway, was made possible by a 2018 $200 million bond program voted on by residents that also includes money for streets, fire stations and a new city administra­tion building.
NWA Democrat-Gazette/DAVID GOTTSCHALK Rufus, a dog owned by Courtney Kremer, director of Animal Services for Springdale, participat­es Tuesday in the groundbrea­king for the new Animal Shelter and Adoption Center for Springdale. The new facility, at 1549 E. Don Tyson Parkway, was made possible by a 2018 $200 million bond program voted on by residents that also includes money for streets, fire stations and a new city administra­tion building.

Newspapers in English

Newspapers from United States