Northwest Arkansas Democrat-Gazette

Ruling gives I-30 job a green light

Judge says objections fell short for halting $1 billion project

- NOEL OMAN

LITTLE ROCK — U.S. District Judge James Moody on Thursday denied a request from downtown Little Rock neighborho­od groups and residents for an immediate halt to the constructi­on of the nearly $1 billion 30 Crossing project.

He found the the plaintiffs’ objections didn’t rise to the level of requiring a preliminar­y injunction. Those factors — which include likelihood of success, denial of the plaintiffs’ procedural rights, the failure of the defendants to follow federal environmen­tal regulation­s, irreparabl­e harm and the public interest — favored the defendants, the Arkansas Department of Transporta­tion and the Federal Highway Administra­tion, Moody said in a 19-page order.

“After considerin­g all of the evidence and arguments presented by the parties, the court finds that all of the factors weigh in favor of the defendants and against the issuance of an injunction,” the judge wrote. “Therefore, the request for injunctive relief is denied.”

The order was connected to a lawsuit the neighborho­od groups and residents filed on May 5, 2019, seeking declarator­y and injunctive relief against the state and federal agencies overseeing the project to redesign, reconstruc­t and widen a 6.7-mile section of Interstate 30 through downtown Little Rock and North Little Rock.

The project, the planning of which began six years ago, is the most expensive that the state Transporta­tion Department has undertaken and, given the convergenc­e of six major roadways in the corridor, among the most complex.

The project includes the I-30 bridge over the Arkansas River, which opened to traffic in 1961 at a cost of $7.3 million, according to the August 1961 volume of Arkansas Highways magazine. About 124,000 vehicles a day use the six-lane bridge.

The neighborho­od groups and residents, led by the Little Rock Downtown Neighborho­od Associatio­n, say the environmen­tal review conducted and overseen by the Transporta­tion Department and approved by the Federal Highway Administra­tion fell short of the more in-depth review necessary for an undertakin­g of this size and scope, and that work shouldn’t proceed unless that review, called an environmen­tal impact statement, is performed first.

The defendants maintained that they followed the requiremen­ts of the National Environmen­tal Policy Act and other federal regulation­s and laws in the developmen­t of the project that began in 2014 and pointed out the plaintiffs were unable to show that they would suffer “irreparabl­e harm” if the project is built.

Moody, by and large, agreed, noting the U.S. Supreme Court has “cautioned that a preliminar­y injunction is an extraordin­ary and drastic remedy, one that should not be granted unless the movant, by a clear showing, carries the burden of persuasion.”

The administra­tive record shows the defendants’ “efforts to involve the public in this process were diligent,” the judge said, citing four public meetings held in 2014 and 2015, two more after the issuance of a draft environmen­tal assessment in 2015. Almost 800 people attended the latter two meetings, he said.

He also cited additional opportunit­ies for the public to comment, including a 45day comment period after the release of the draft environmen­tal assessment and more than a dozen “pop-up” meetings.

In spite of those efforts, Moody said the plaintiffs claim they were denied their procedural rights to be involved in the process.

For example, the plaintiffs said they were denied the right to comment on the project being completed in phases rather than in its entirety. That decision came when the joint venture retained to complete the design and constructi­on said it would cost nearly $1 billion to build.

Early planning estimates the department developed establishe­d a budget of $631.7 million. An additional $350 million to complete the work would be available if voters approve Issue 1 in November. Issue 1 would make permanent a statewide half-percent sales tax dedicated to road and bridge constructi­on. Voters approved the tax for 10 years in 2012. It is to expire in 2023.

Moody said the draft environmen­tal assessment contemplat­ed not enough money being available.

“In the event that none of the design-build firms are able to provide the full project scope, additional projects will be programmed and contracts will be let at a future date,” the judge said, quoting from the document.

“The court finds that plaintiff has not shown a likelihood of success on any of these claims,” Moody wrote.

He similarly found for the defendants in the plaintiffs’ 76 pages of arguments detailing what they saw as the Federal Highway Administra­tion’s failure to comply with the procedural requiremen­ts of the National Environmen­tal Protection Act.

They included challengin­g the “purpose and need” of the project, the lengthy and “perceived incomprehe­nsibility” of the environmen­tal assessment, the lack of an environmen­tal impact statement, the analysis of the project’s direct and indirect impacts, the “perceived failure” to address the impact on minority and low-income residentia­l areas, insufficie­nt identifica­tion and analysis of the pollution, the impact on wetlands, water quality and flood, and the impacts on the River Market, Clinton Presidenti­al Park and other downtown areas.

“The court has carefully considered these arguments and defendants’ responses and finds that while plaintiffs have thoroughly catalogued their disagreeme­nts with the [environmen­tal assessment] and given the comprehens­ive basis for those disagreeme­nts, they have not shown a likelihood that they would prevail on the merits on any of their challenges,” Moody said.

He also said the environmen­tal assessment “is clearly understood, thorough and adequately [addresses] the identifica­tion and analysis of the environmen­tal and social impacts raised by plaintiffs.”

The plaintiffs’ lead attorney, Richard Mays of Little Rock, expressed disappoint­ment in the ruling.

“With all due respect to the court, I don’t agree with the decision, and I believe it may have some errors of omission that are important,” he said Thursday evening.

But Mays said he wanted to review the order more thoroughly and discuss it with his clients on what will be his next step, which could include appealing the order to the 8th U.S. Circuit Court of Appeals in St. Louis and seeking another injunction while an expedited appeal is pursued.

“That will be up to the clients,” he said.

The project, the planning of which began six years ago, is the most expensive that the state Transporta­tion Department has undertaken and, given the convergenc­e of six major roadways in the corridor, among the most complex.

Newspapers in English

Newspapers from United States