Orlando Sentinel

Osceola takes lead studying land in deal for Split Oak road

- By Kevin Spear

Following a state agency’s decision to allow a toll road in Split Oak Forest, the conservati­on property’s fate now shifts to Osceola County staffers behind closed doors for an indefinite period that offers no window for public involvemen­t.

With its 4-0 vote to permit the road and the donation of 1,550 acres as compensati­on, the Florida Communitie­s Trust said Split Oak owners Orange and Osceola counties must provide, among many items, an environmen­tal site assessment and a plan for how the forest would be cared for.

Osceola County has assumed the task of the environmen­tal assessment, and county spokespers­on Mark Pino said no deadline has been set for addressing the list of requiremen­ts by the Trust for Split Oak Forest.

“This entire process is going to take many months,” Pino said, “starting with establishi­ng an understand­ing of FCT wants.”

A 1.3-mile stretch of the 1,700-acre Split Oak Forest in east Orange and Osceola counties is targeted for constructi­on of a toll road sought and subsidized by Tavistock Developmen­t Co. and its partner Deseret Ranches for their enormous rollout of subdivisio­ns in east Osceola.

As compensati­on for the proposed road intrusion, Tavistock and Deseret would donate 1,550 acres of conservati­on lands in an irregularl­y shaped parcel that adjoins Split Oak and sweeps to the east and north.

That offer was decried by many speakers April 20 at the Florida Communitie­s Trust meeting in Tallahasse­e as a shame, as poorly understood or as not as ecological­ly valuable as the 60 acres of Split Oak that would be paved and another 100 acres that would be separated from the forest.

The Trust holds some authority but not ownership for Split Oak, according to the agency’s attorney, because it provided Orange and Osceola a grant and loan in the 1990s to buy the property.

The counties now own the forest jointly and rely on the Florida Fish and Wildlife Conservati­on Commission to manage it as a non-hunting wildlife refuge, which is being pinched on its south end by accelerati­ng developmen­t.

Pino said the county is preparing to hire a consultant to write the environmen­tal assessment that the Trust demanded.

The toll road proposed for crossing the southwest corner of Split Oak is an extension of the Osceola Parkway and is a project of the Central Florida Expressway Authority based in Orlando.

While all of the road impact would be within Osceola’s portion of the forest, the largest share of the 1,550 acres offered as a donation, or more than 960 acres, are in

Orange County.

In a 2020 election, 86% of Orange voters said the county should protect Split Oak from developmen­t.

As Osceola proceeds with an environmen­tal assessment, Orange County will not be part of or have any say in that effort, according to county officials.

In a memo Monday to county commission­ers, the manager of the county’s Environmen­tal Division, David Jones, said that future actions may include decisions on whether to accept a donation of land and whether to revise agreements for management of Split Oak.

“At this time, there is not a definitive timeframe for when these items may come to the Orange County Board of County Commission­ers,” Jones said.

An evaluation of the 1,550 acres was performed in 2019 by Breedlove, Dennis & Associates Inc. of Winter

Park, a company that specialize­s in work on behalf of developers and was hired by Tavistock for the Split Oak assessment.

The firm’s report states that the toll road would destroy or harm nearly 120 acres of forest or other dry habitat and about 40 acres of wetlands.

Of the 1,550 acres identified for a donation, the report states, 489 acres are potential habitat for gopher tortoises and 909 acres are wetlands that rank high in value, according to evaluation criteria used statewide.

 ?? JOE BURBANK/ORLANDO SENTINEL ?? The bulldozed shoreline at the Bridgewalk housing developmen­t under constructi­on at the western border of the Split Oak Forest Wildlife and Environmen­tal Area in St. Cloud.
JOE BURBANK/ORLANDO SENTINEL The bulldozed shoreline at the Bridgewalk housing developmen­t under constructi­on at the western border of the Split Oak Forest Wildlife and Environmen­tal Area in St. Cloud.
 ?? CENTRAL FLORIDA EXPRESSWAY AUTHORITY ?? A proposal to build Osceola Parkway across the south portion of Split Oak Forest is paired with an offer by developers to donate 1,550 acres, depicted in the darker green, as compensati­on for the road’s intrusion. This map shows the extensive developmen­t planned and already crowding at Split Oak’s south boundary where the road would be built. It also depicts Cyrils Drive, which will carry much of the traffic from the developmen­t.
CENTRAL FLORIDA EXPRESSWAY AUTHORITY A proposal to build Osceola Parkway across the south portion of Split Oak Forest is paired with an offer by developers to donate 1,550 acres, depicted in the darker green, as compensati­on for the road’s intrusion. This map shows the extensive developmen­t planned and already crowding at Split Oak’s south boundary where the road would be built. It also depicts Cyrils Drive, which will carry much of the traffic from the developmen­t.