NASA aiming for Saturday launch of new moon rocket

- By Richard Tribou

NASA officials are more confident that the Saturday launch attempt of its Artemis 1 mission to the moon will be successful after poring over data that led to Monday’s scrub, while weather may cooperate as well.

In fact, Monday’s scrub at Florida’s Kennedy Space Center might have been unnecessar­y after NASA discovered the main reason for it was inaccurate sensor readings. Although there were several issues during the countdown that caused stress on the launch teams, the false reading was that one of the four RS-25 engines at the base of the Space Launch System rocket core stage had not cooled enough for a safe launch.

“We had some sensors that didn’t tell us what we thought,” said NASA SLS chief engineer John Blevins during a mission update Thursday. “We did the right thing by standing down with that uncertaint­y on Monday, but we have confirmed that we did have good flow through those engines. We know we can chill those engines. We’re ready to proceed.”

Mr. Blevins said those sensors, which are unreachabl­e on the launch pad, will be ignored for Saturday’s attempt. The two-hour launch window for liftoff opens at 2:17 p.m. with a backup launch attempt available on Monday during a 90-minute window that opens at 5:12 p.m.

Weather for Saturday’s attempt, though, is looking better than earlier forecasts, with the Space Launch Delta 45 weather squadron giving it a 60% chance for good conditions

at the opening of the window, but improving later in the afternoon.

“I do expect to make some no-go calls at some point,” said SLD 45 weather officer Melody Lovin on Friday. “However, as that East Coast sea breeze drifts farther inland, we do expect clearing on the backside of that, and that is the reason why we are turning the forecast to more of an 80% favorabili­ty at the end of the launch window.”

If it delays, the Monday forecast odds are set to 70%.

“I do not expect weather to be a showstoppe­r by any means for either launch window,” she said.

Crowds on the Space Coast to watch the launch could approach 400,000, according to the Brevard County Emergency Operations Center with traffic delays expected on either side of the attempt. That would more than double the estimated crowd that left town disappoint­ed on Monday.

The Monday scrub in some ways was due to issues faced during tanking that then pressed NASA teams for time. That included detection of a potential

hydrogen leak along with weather that forced holds in the countdown. Later in the count, the test of what is known as the bleed system of supercoole­d liquid hydrogen into the engines proved too complicate­d to work around in the time remaining before liftoff.

While mission managers have addressed the possible hydrogen leak and determined the engines did in fact cool during the bleed test despite the sensor readings, more time in the countdown clock has been added to better troublesho­ot issues that may arise.

“So this is a test flight, right? And so while I feel very good about our procedures, when you look the team in the eye, they’re

ready,” said Jeremy Parsons, deputy manager for NASA’s Exploratio­n Ground Systems.

The goal if the rocket launches Saturday is to send the SLS rocket topped with the uncrewed Orion capsule on a 38-day mission to orbit the moon several times before it heads back for a splashdown on Earth in the Pacific Ocean on Oct. 11.

 ?? Brynn Anderson/Associated Press ?? The NASA moon rocket stands on Pad 39B at the Kennedy Space Center in Cape Canaveral, Fla., on Friday in preparatio­n for the Artemis 1 mission to orbit the moon.
Brynn Anderson/Associated Press The NASA moon rocket stands on Pad 39B at the Kennedy Space Center in Cape Canaveral, Fla., on Friday in preparatio­n for the Artemis 1 mission to orbit the moon.