La. project aims to restore miles of land lost to coastal flooding

- By Kevin McGill

NEW ORLEANS — Nearly $3 billion in settlement money from the BP Deepwater Horizon disaster that devastated the Gulf Coast and killed hundreds of thousands of marine animals is now funding a massive ecosystem restoratio­n in southeaste­rn Louisiana’s Plaquemine­s Parish.

The sparsely populated land divided by the Mississipp­i River delta, is marbled by bayous and bays. Farms, fishing camps and shrimp boats share the region with oil rig supply vessels and industrial storage. And it’s about to host a vast undertakin­g meant to mimic Mother Nature: Enormous gates will be soon be incorporat­ed into a flood protection levee.

The aim is to divert some of the river’s sediment-laden water into a new channel and guide it into the Barataria Basin southeast of New Orleans.

If it works, the sediment will settle out in the basin and gradually restore land that has been steadily disappeari­ng for decades. State coastal officials call it a first

-of-its-kind project they are certain will work, even as climate change-induced rising sea levels threaten the disappeari­ng coast.

Gov. John Bel Edwards called it the largest such ecosystem restoratio­n project in the state’s history. “Quite frankly I’m not aware of one on this scale any where in

the country and they’re are few in the world that can match the size of this project,” he said at Thursday’s groundbrea­king.

Bren Haase, chair of Louisiana’s Coastal Protection and Restoratio­n Authority, estimates the project will build from 20 square miles to 40 square miles over the next 30 to 50 years.

The U.S. Army Corps of Engineers projected creating of as much as 21 square miles by 2070. Subsidence and sea level rise will diminish the returns, so much so that a net loss of land remains likely. But that can be seen as a factor increasing the importance of the effort.

“As land loss accelerate­s due to sea-level rise and subsidence, more of the remaining wetland area would be attributed to diversion operations,” the statement’s executive summary said.

Coastal experts say south

Louisiana was built by sediment deposited as the river continuous­ly altered its own meandering course over thousands of years.

Efforts to constrain the river with flood protection levees and huge flow-control structures safeguarde­d cities and communitie­s that developed along the banks as the river became a medium of navigation and commerce. But the developmen­t also stopped the millenniao­ld process of building land naturally.

That is a major reason Louisiana’s marshy coastal wetlands have given way to growing swaths of open water, posing a myriad of environmen­tal concerns. Those concerns include worry about the erosion of land that serves as a natural hurricane bufferfor New Orleans.

“The Mississipp­i River built Louisiana –- and finally reconnecti­ng it with coastal

areas that are currently starved of freshwater and sediment will ensure our future,” U.S. Rep Garrett Graves, a Republican, said in a news release. Mr. Graves supported the project in Congress and served as a top coastal restoratio­n official under former Gov. Bobby Jindal.

Channeling water from the Mississipp­i into the basin poses environmen­tal and economic problems, too. Even as it granted permits for the project, the Corps noted the environmen­tal costs of introducin­g nonsalty river water into coastal areas where aquatic animals thrive in salty or brackish water. The changes could kill bottlenose dolphins and have varying effects on fish and sea turtles. Fishermen have long opposed the project because of its expected effects on shrimp and oysters.

Kerri Callais, a board member for the Save Louisiana Coalition, which opposes the diversion, is among opponents who favor other coast-building methods, including rebuilding barrier islands and using pipelines to pump sediment to land-depleted areas.

“These are projects that we know will build land, will not take decades, and will not take the livelihood­s, culture, and heritage of our citizens away,” Ms. Callais, a member of the governing

council in neighborin­g St. Bernard Parish, said in an email.

Opposition has remained despite state promises of efforts to mitigate harm. On Tuesday, for instance, coastal officials outlined $10 million in planned spending on a variety of projects to aid fishers and oyster harvesters who will have to change the areas where they work or make other adjustment­s as a result of the project. Millions more in spending is planned to help communitie­s near the river that might see increased flood threats from the project, including elevation of roadways.

Some environmen­tal groups see the potential benefits. Matt Rota, senior policy director for the nonprofit Healthy Gulf, said the project will use less energy than sediment pumping, and he acknowledg­ed the need to work with the river on its natural ability to build land.

“This diversion, if it’s successful, is more passive,” Mr.Rota said, “which means it can keep going, whether or not we have money or the fuel.”

Still, Mr. Rota said, Healthy Gulf wants to see more done to help locals who depend on fisheries and oysters for their livelihood­s. He said state and federal government­s must also work harder to limit pollution upriver.

 ?? Alex Brandon/Associated Press ?? Coastal erosion has broken through the marsh grass in the Barataria Basin near Port Fourchon, La. Officials are breaking ground in southeast Louisiana on a nearly $3 billion project to fight coastal wetland loss.
Alex Brandon/Associated Press Coastal erosion has broken through the marsh grass in the Barataria Basin near Port Fourchon, La. Officials are breaking ground in southeast Louisiana on a nearly $3 billion project to fight coastal wetland loss.
 ?? Coastal Protection and Restoratio­n Authority via AP ?? This computer rendering provided by Louisiana's Coastal Protection and Restoratio­n Authority depicts the planned MidBaratar­ia Sediment Diversion project, which, when completed in five years, will channel sediment-laden Mississipp­i River water into southeast Louisiana's Barataria Basin.
Coastal Protection and Restoratio­n Authority via AP This computer rendering provided by Louisiana's Coastal Protection and Restoratio­n Authority depicts the planned MidBaratar­ia Sediment Diversion project, which, when completed in five years, will channel sediment-laden Mississipp­i River water into southeast Louisiana's Barataria Basin.