Mexico plans to start awarding the constructi­on of its seventh refinery as soon as March 2019, President Andres Manuel Lopez Obrador said over the weekend at an event at the Dos Bocas port in Tabasco, even as the nation’s refining system is operating at its lowest levels in three decades.

Unveiling a plan for the nation’s refining system, Lopez Obrador said Mexico will invest $8 billion in the new processing facility at Dos Bocas. “We are going to start the bidding process for the refinery by March at latest,” he said to a cheering crowd Sunday in the sun-drenched town in the Gulf of Mexico, reiteratin­g his intentions to boost fuel self-sufficienc­y and end long-term declines in oil output. Mexico’s oil production, on track for its 14th consecutiv­e yearly decline, will rise “realistica­lly” to 2.4 million barrels a day by 2024, he said.

Lopez Obrador said a lot of 566 hectares of federal land is ready for the new plant, which will have crude processing capacity of 340,000 barrels a day, making it Mexico’s biggest refinery. It will include 17 processing plants, and 93 storage tanks or facilities, and link up to the Dos Bocas maritime terminal. A pipeline will be built connecting the refinery to the port.

Mexico’s president, known as AMLO, isn’t done. On Monday, he said he’ll soon reveal plans to increase oil production, during a trip to the southeaste­rn state of Campeche. AMLO last week called for a hiatus on oil auctions until foreign companies show results from the previously awarded contracts.

Companies such as Ica Fluor, a joint venture between Mexico’s Empresas ICA SAB and Fluor Corp. in the U.S., and U.S.-based Bechtel Group Inc., have previously expressed interest in participat­ing in the public tender for the refinery project. Lopez Obrador didn’t say if the state-owned oil company, Petroleos Mexicanos, will operate the new facility.

“In three years we will be producing the gasoline that we consume in the country, so that now we can lower the prices of the fuel,” he said.

Lopez Obrador also said the government will increase Pemex’s budget by 75 billion pesos for 2019 so the company will be able to invest in a series of new projects to improve its operations. He reiterated his government will submit the 2019 budget to the Congress on Dec. 15 and said the nation won’t use the oil contingenc­y fund to finance the new oil policy.

Lopez Obrador said Pemex will overhaul its six refineries and bring gasoline production up to 600,000 barrels a day by mid-2020, according to an emailed statement from the energy ministry. In October, Pemex produced 171,700 barrels a day of gasoline.

The Salamanca refinery will undergo work to bring capacity to 75 percent by the end of next year. Pemex will replace an FCC unit and rehabilita­te the Mina 1 unit at the Minatitlan refinery to increase capacity by mid-2019. The Madero plant, which has undergone an intensive maintenanc­e cycle this year, will start operating again in January.

Cadereyta and Salina Cruz will require extensive maintenanc­e, with the latter expected to reach 70 percent of capacity in December next year. At Tula, where a joint-venture for a coker unit has yet to be finalized, the government will restart the H-Oil unit.

 ?? Marco Ugarte / Associated Press ?? Mexico President Andres Manuel Lopez Obrador said he’ll soon reveal plans to increase oil production.
Marco Ugarte / Associated Press Mexico President Andres Manuel Lopez Obrador said he’ll soon reveal plans to increase oil production.